8.A. - Page 38 <br /> 7.7 Insurance: <br /> Seller shall obtain and maintain the policies of insurance in amounts and with coverage as <br /> set forth in Exhibit E [Insurance Requirements]for the term of this Agreement. <br /> 7.8 Commissioning Tests: <br /> Seller shall comply with all applicable Local Electric Utility requirements for pre- <br /> operational testing. In addition, no later than fourteen (14) days prior to conducting its <br /> Commissioning Tests, Seller shall notify Buyer of the date on which it intends to conduct <br /> such tests. Within seven (7) days of the successful completion of Seller's Commissioning <br /> Tests, Seller shall provide to Buyer written notification of the Actual Commercial <br /> Operation Date, including any relevant data demonstrating that Actual Commercial <br /> Operation has occurred. Buyer has the right to be present during any Commissioning Test, <br /> and to receive all information, including meter and performance data associated with <br /> such tests. Seller may change the date for such tests upon written notice to Buyer, <br /> provided that Buyer has at least fourteen (14) days' notice of the date of such tests. <br /> 7.9 Obligation to Interconnect: <br /> Seller shall be responsible for the interconnection of the Facility to the Project Site <br /> electrical system and shall be solely responsible for all equipment, maintenance, and <br /> repairs associated with such interconnection equipment in accordance with the terms <br /> and conditions of this Agreement. Buyer shall at all times own and be responsible for the <br /> operation and maintenance of the Project Site electrical system at and from the Delivery <br /> Point. <br /> Seller,with Buyer's assistance, shall, at its own cost and expense, enter into net metering <br /> arrangements by executing such agreements, including Interconnection Agreements, as <br /> may be required by the Local Electric Utility to permit the interconnection of the Facility <br /> with the Project Site electrical system and to allow any output of the Facility not <br /> consumed by the Project Site to flow to the Local Electric Utility. Seller shall promptly <br /> provide copies of such agreements and arrangements to Buyer when executed. Seller <br /> shall be responsible for all costs under any Interconnection Agreement and any other <br /> agreements with the Local Electric Utility including but not limited to the costs of any <br /> upgrades to the Transmission System associated with the Interconnection of the Project <br /> Site electrical system. Per California net metering laws,there are no interconnection fees. <br /> 7.10 Facility Conformance to Buyer Specifications. Seller shall assure that each Facility remains <br /> in conformance with the most recent version of the as-built drawings approved by the <br /> Buyer and all specifications and requirements of this Agreement during the Term, <br /> including when maintenance is performed or when modifications are implemented.Seller <br /> has the right to modify the design of the Facility subject to the Buyer's approval, not to <br /> unreasonably conditioned, delayed, or withheld. Buyer may, at any time, prepare and <br /> provide to Seller a letter or notice of any observed defects, deficiencies or deviations <br /> ATTY/AGR/2015.012/POWER PURCHASE AGREEMENT-CEI SOLAR ONE LLC <br /> REV:01-21-15 MLG <br /> Page 30 of 55 <br />