25. Remedies. <br /> 25 .1 City may proceed to complete the Work by contract or other method City <br /> considers advisable, at the sole expense of Developer. Developer, immediately upon demand, <br /> shall pay the costs and charges related to the Work and any subsequent repairs. City, without <br /> liability for doing so, may take possession of and utilize in completing the Work and repairs, if <br /> any, such materials and other property belonging to Developer as may be on or about the Property <br /> and necessary for completion of the work. In the event of default, the financial institution holding <br /> the securities shalt be liable to City to pay the face amount of the security, as specified under <br /> Section 13. <br /> 252 City may bring legal action to compel performance of this Agreement and <br /> recover the costs of completing the Work and/or repairs, if any, including City's administrative <br /> and legal costs or pursue any other action at law or equity. <br /> 253 Developer agrees that if legal action is brought by City under this section of the <br /> Agreement, Developer shall pay all of the costs of suit, reasonable attorney fees, arbitration costs <br /> and such other costs as may be determined by the court or arbitrator. <br /> 25 .4 No failure on the part of City to exercise any right or remedy hereunder shall <br /> operate as a waiver of any other right or remedy that City may have hereunder. <br /> 25 5 The rights and remedies of City are cumulative, and the exercise by City of one <br /> or more of such rights or remedies shall not preclude the exercise by it, at the same or different <br /> times, of any other rights or remedies for the same default or any other default. <br /> 26. Final Drawings. Upon completion of the Work and prior to final acceptance, Developer <br /> shall deliver to City a set of "as-built" drawings consistent with the Conditions. These drawings shall be <br /> in a form acceptable to the City Engineer, shall be certified as being "as-built" and shall reflect the Work <br /> as actually constructed, with any and all changes incorporated therein. Said drawings shall be signed and <br /> sealed as accurate by the engineer of record. <br /> 27. Monuments. All pipes and monuments shown on the Final Map which are destroyed or <br /> displaced during construction operations shall be replaced by Developer at the time of the final inspection <br /> of the Improvements, if any. <br /> 28. Attorneys' Fees. Should any legal action or arbitration be brought by either party because <br /> of breach of this Agreement or to enforce any provision of this Agreement, the prevailing party shall be <br /> entitled to all costs of suit, reasonable attorneys' fees, arbitration costs and such other costs as may be <br /> determined by the court or arbitrator. <br /> 29. Notices. Any notices relating to this Agreement shall be given in writing and shall be <br /> deemed sufficiently given and served for all purposes when delivered personally or by generally <br /> recognized overnight courier service, or five (5) days after deposit in the United States mail, certified or <br /> registered, return receipt requested, with postage prepaid, addressed as follows: <br /> To the Developer: West Oakwood, LLC <br /> 865 Sweeney Ave <br /> Redwood City, CA 94063 <br /> Attn: Samuel Kwok <br /> REV: 11-06-14 VR <br /> Page 10 of 18 <br /> ATTY/AGR.2014.244/Rossi Lane Improvement Agreement <br />