Laserfiche WebLink
8.1.A. - Page 2 <br /> suspension of construction for the Bair Island Storm Drain Pump Station on October 1st <br /> 2015. <br /> At their December 10, 2015 meeting, the SVCW Commission declared an "Emergency <br /> Condition" after SVCW staff detected leaks on their sewer pipe near the SVCW- <br /> operated Maple Street Sanitary Sewer Pump Station. SVCW's emergency condition <br /> meant that SVCW's original sewer force main near the Bair Island Storm Drain Pump <br /> Station would need to be operational and the City would need to temporarily suspend <br /> the construction of BISDPS again. In August 2016, the sanitary sewer force main that <br /> was near the BISDPS project site was fully decommissioned by SVCW and the BISDPS <br /> construction was able to resume. <br /> ANALYSIS <br /> During the suspension of the BISDPS project, the main supplier for the specialized <br /> equipment and material needed for the pump station was not able to come to an <br /> agreement with the general contractor, Sanco Pipeline Inc. As a result, the previous set <br /> of materials and equipment submitted and reviewed by the City and Carollo were no <br /> longer valid. New submittal packages were provided by the general contractor that <br /> included pump station components such as the pumps, sensors, generators, and motor <br /> controls. This unexpected change of supplies resulted in additional time and cost by the <br /> design engineer, Carollo, to review all the new material and equipment submittals and <br /> make recommendations of acceptability. Additional review and recommendations may <br /> still be needed from the consultant, including to evaluate the manufacturers' manuals for <br /> the operations and maintenance of the various equipment that will be installed for the <br /> pump station. Furthermore, services may be needed by the City after construction is <br /> complete, such as special investigation and technical consulting to assess and provide <br /> recommendations to address issues that may arise after the pump station is accepted <br /> and operated by the City. <br /> The proposed amendment expands the original scope of services to include additional <br /> engineering support services by Carollo during construction, as well as after <br /> construction. The consultant's charges will be based on Carollo's hourly rate schedule. <br /> Staff believes the additional scope of work represents a sound level of effort and is <br /> essential to delivering a complete Council-approved capital improvement program. <br /> ALTERNATIVES <br /> Council may choose not to approve the proposed amendment to the agreement with <br /> Carollo Engineers, Inc. and direct staff to find alternate means of completing the work, <br /> or modify the scope of work for the amended professional services agreement. <br /> FISCAL IMPACT <br /> Funds for this project were appropriated under Traffic Mitigation Fees Fund— Blomquist <br /> Avenue Extension Project, which has an available balance of $878,231.69, as of August <br /> 31, 2016. <br />