My WebLink
|
Help
|
About
|
Sign Out
Browse
Search
Agmt90 DDA Sequoia Station
RedwoodCity
>
City Clerk
>
Agreements
>
1990-1999
>
1990
>
Agmt90 DDA Sequoia Station
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
10/19/2017 12:13:32 PM
Creation date
9/13/2017 4:36:22 PM
Metadata
Fields
Template:
Agreement
Contractor Name
Sequoia Station Developers, Inc
PROJECT NAME
Sequoia Station
RMP File Number
405
Date
4/10/1990
Amendment
Yes
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
94
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
Show annotations
View images
View plain text
29. City parcels and Acquisition Within 10 days of step 22 <br />Parcels conveyed to Developer but in no event before Agency <br />(fee title or possession) acproval of evidence of <br />financing. <br />30. Developer submits plans and Within 30 days of step 17. <br />applications for all other <br />permits (including but not <br />limited to demolition, grading, <br />building, and on and off-site <br />improvement plans). <br />31. Developer notified by letter if Within 10 days of step 25. <br />application(s) complete/incomplete. <br />32. If necessary, Developer revises and Within 10 days of step 26. <br />resubmits. <br />33. City staff approves the permit Within 45 days of receipt <br />applications as submitted or with of a complete application. <br />staff" amendments. <br />34. City/Agency issue permits Within 15 days of step 28. <br />evidencing notice to proceed. <br />35. Developer begins site clearance Within 90 calendar days of <br />and development. step 29. <br />36. Developer completes side Within 730 calendar days of <br />de.elcpment step 30. <br />37. Developer requests Certificate Within 10 days of step 31. <br />of Completion. <br />38. Agency notified by letter if Within 10 days of step 32. <br />project is complete/incomplete. <br />39. Developer completes final items, Within 20 days of step 33. <br />if any, identified in step 33. <br />40. Agency issues Certificate of Within 10 days of the end of <br />Completion. step 34. <br />Amended 3/30/90 <br />4/4/90 <br />
The URL can be used to link to this page
Your browser does not support the video tag.