Deliverables: <br />• Monthly progress reports accompanying the invoices. <br />• Public meeting presentation materials. <br />• Meeting/hearing attendance. <br />Project Schedule <br />AECOM has prepared a proposed project schedule on the following page. The timeline <br />shows an overall 12 -13 -month duration for CEQA review, with an Initial Study and <br />NOP released within the first 4-1/2 months. While the Initial Study is in preparation and <br />during its public review, work on the EIR will have commenced to compress the overall <br />schedule. This schedule may be adjusted upon mutual agreement of the City and <br />AECOM without an amendment to this Agreement, e.g. to allow for additional time for <br />City review of documents. <br />Level of Effort <br />AECOM has provided a detailed cost spreadsheet on the two pages following the <br />anticipated schedule duration. The hours and costs reflect the assumptions identified in <br />the preceding scope of work. <br />Page 21 of 37 <br />ATTY/AGR/2018.270/AECOM PSA <br />REV: 12-07-18 PR <br />