<br />B. Liauidated Damages <br />1. Agency and Contractor recognize that time is of the essence of this <br />Agreement and that Agency will suffer financial loss in the form of lost <br />revenues, contract administration expenses (including project management <br />and consultants' expenses), delay and loss of public use, if the Work is not <br />completed within the time specified in paragraph 1I1.A.1 above plus any <br />extensions thereof allowed in accordance with the Contract documents. <br />Consistent with Section 00700 (General Conditions), Contractor and Agency <br />agree that because of the nature of the Project, it would be impractical or <br />extremely difficult to fix the amount of actual damages incurred by Agency <br />because of a delay in completion of the Work. <br /> <br />2. Accordingly, Agency and Contractor agree that Contractor shall pay Agency <br />$500.00 for each Day that expires after the time specified in Paragraph <br />II I. A. 1 of this Section 00520 for Contractor to achieve Substantial <br />Completion, until such date as contractor achieves Substantial Completion. <br /> <br />C. Liquidated damages for delay shall only cover and be in lieu of the actual damages <br />suffered by Agency as a result of delay referenced above. Liquidated damages <br />shall not cover the cost of completion of the Work, damages resulting from defective <br />work, cost of temporary replacement facilities, damages suffered by others who <br />then seek to recover their damages from City (for example, delay claims of other <br />contractors or subcontractors), and defense costs thereof. <br /> <br />IV. CITY'S ENGINEER AND REPRESENTATIVES <br />Reserved <br /> <br />V. CONTRACTOR'S REPRESENTATIONS AND WARRANTIES <br /> <br />In order to induce Agency to enter into this Agreement, Contractor makes the following <br />representations and warranties: <br /> <br />A. Contractor has visited the Site and has examined thoroughly and understood the <br />nature and extent of the Work, Site, locality, actual conditions, as built conditions, <br />and all local conditions and federal, state and local laws and regulations that in any <br />manner may affect cost, progress, performance or furnishing of Work or which <br />relate to any aspect of the design and the means, methods, techniques, sequences <br />or procedures of construction to be employed by Contractor and safety precautions <br />and programs incident thereto. <br /> <br />B. Contractor has examined thoroughly and understood all reports of exploration and <br />tests of subsurface conditions, drawings or reports, available for design and <br />construction purposes, of physical conditions, or which may be apparent at the Site <br />and accepts the determination set forth in these Sections and Section 00700 <br />(General Conditions) of the limited extent of the information contained in these <br />Sections upon which the Contractor may be entitled to rely. Contractor agrees that <br />except for the information so identified, Contractor does not and shall not rely on <br />any other information contained in these Sections. <br /> <br />C. Contractor has considered the physical conditions at or contiguous to the Site or <br />otherwise which may affect the cost, progress, performance or furnishing of Work, <br />as Contractor considers necessary for the performance or furnishing of Work at the <br />Contract Sum, within the Contract Time and in accordance with the other terms and <br />conditions of Contract documents, including specifically the provisions of the <br />General Conditions. <br /> <br />Page 2 of 4 <br />