Laserfiche WebLink
ID Task Task Name Duration Total Slack Start Finish <br />1 Project Funding 392 days 0 days Thu 11/30/23 Sat 5/31/25 <br />2 RAISE 150 days 0 days Thu 11/30/23 Thu 6/27/24 <br />3 NOFO Release 0 days 581 days Thu 11/30/23 Thu 11/30/23 <br />4 Application Due Date 0 days 517 days Wed 2/28/24 Wed 2/28/24 <br />5 Anticipated Award 0 days 431 days Thu 6/27/24 Thu 6/27/24 <br />6 Port Inf. Dev. Program (PIDP)221 days 0 days Wed 12/27/23 Thu 10/31/24 <br />7 NOFO Release 0 days 562 days Wed 12/27/23 Wed 12/27/23 <br />8 Application Due Date 0 days 473 days Tue 4/30/24 Tue 4/30/24 <br />9 Anticipated Award 0 days 341 days Thu 10/31/24 Thu 10/31/24 <br />10 Safe Streets & Roads for All (SS4A)206 days 0 days Fri 2/16/24 Sat 11/30/24 <br />11 NOFO Release 0 days 525 days Fri 2/16/24 Fri 2/16/24 <br />12 Application Due Date 0 days 451 days Thu 5/30/24 Thu 5/30/24 <br />13 Anticipated Award 0 days 320 days Sat 11/30/24 Sat 11/30/24 <br />14 Active Transportation Program (ATP)161 days 0 days Thu 3/21/24 Fri 11/1/24 <br />15 Call for Projects Release 0 days 501 days Thu 3/21/24 Thu 3/21/24 <br />16 Application Due Date 0 days 439 days Mon 6/17/24 Mon 6/17/24 <br />17 Anticipated Award 0 days 340 days Fri 11/1/24 Fri 11/1/24 <br />18 Trace Corridor Enhance. Program (TCEP)242 days 0 days Thu 6/27/24 Sat 5/31/25 <br />19 Call for Projects Release 0 days 431 days Thu 6/27/24 Thu 6/27/24 <br />20 Application Due Date 0 days 320 days Sat 11/30/24 Sat 11/30/24 <br />21 Anticipated Award 0 days 190 days Sat 5/31/25 Sat 5/31/25 <br />22 Final Design 490 days 0 days Thu 12/7/23 Wed 10/22/25 <br />23 Commence with Final Design and R/W 0 days 86 days Thu 12/7/23 Thu 12/7/23 <br />24 65% PS&E (Structures)115 days 86 days Thu 2/8/24 Wed 7/17/24 <br />25 65% Structure Design Plans/Calcs 80 days 86 days Thu 2/8/24 Wed 5/29/24 <br />26 65% Quantities Preparation 5 days 86 days Thu 5/30/24 Wed 6/5/24 <br />27 65% Special Provisions 5 days 86 days Thu 6/6/24 Wed 6/12/24 <br />28 65% Internal Review 5 days 86 days Thu 6/13/24 Wed 6/19/24 <br />29 Submit 65% Structural Package to ESC 0 days 86 days Wed 6/19/24 Wed 6/19/24 <br />30 ESC Review 65% PSE Structual Package 20 days 86 days Thu 6/20/24 Wed 7/17/24 <br />31 95% PS&E 220 days 86 days Thu 12/7/23 Wed 10/9/24 <br />32 AECOM Contract Amend.45 days 86 days Thu 12/7/23 Wed 2/7/24 <br />33 PMT Review of AECOM Contract Amend.10 days 86 days Thu 2/8/24 Wed 2/21/24 <br />34 Ad Hoc Approval of AECOM Contract Amend 0 days 86 days Wed 2/21/24 Wed 2/21/24 <br />35 City Attorney Execute Contract Amend 10 days 86 days Thu 2/22/24 Wed 3/6/24 <br />36 Existing Conditions Update 15 days 211 days Thu 3/7/24 Wed 3/27/24 <br />37 Bicycle Facility Design Resolution 15 days 211 days Thu 3/28/24 Wed 4/17/24 <br />38 Design Reports 60 days 86 days Thu 3/7/24 Wed 5/29/24 <br />39 Design Plan Sheets 75 days 86 days Thu 3/7/24 Wed 6/19/24 <br />40 Specs & Special Provisions 50 days 86 days Thu 5/9/24 Wed 7/17/24 <br />41 Quantities & Cost Estimate 50 days 86 days Thu 5/9/24 Wed 7/17/24 <br />42 Finalize 95% PS&E 20 days 86 days Thu 7/18/24 Wed 8/14/24 <br />43 Submit 95% PS&E 0 days 86 days Wed 8/14/24 Wed 8/14/24 <br />44 Caltrans District Review 95% PS&E 40 days 86 days Thu 8/15/24 Wed 10/9/24 <br />45 ESC Review 95% PS&E Comments 30 days 96 days Thu 8/15/24 Wed 9/25/24 <br />46 100% PS&E 150 days 86 days Thu 10/10/24 Wed 5/7/25 <br />47 Review 95% PS&E Comments 10 days 86 days Thu 10/10/24 Wed 10/23/24 <br />48 Address 95% PS&E Comments 60 days 86 days Thu 10/24/24 Wed 1/15/25 <br />49 Finalize 100% PS&E 40 days 86 days Thu 1/16/25 Wed 3/12/25 <br />11/30 <br />2/28 <br />6/27 <br />12/27 <br />4/30 <br />10/31 <br />2/16 <br />5/30 <br />11/30 <br />3/21 <br />6/17 <br />11/1 <br />6/27 <br />11/30 <br />5/31 <br />12/7 <br />6/19 <br />2/21 <br />8/14 <br />2023 2024 2025 2026 2027 2028 2029 2030 2031 <br />Task <br />Split <br />Milestone <br />Summary <br />Project Summary <br />Inactive Task <br />Inactive Milestone <br />Inactive Summary <br />Manual Task <br />Duration-only <br />Manual Summary Rollup <br />Manual Summary <br />Start-only <br />Finish-only <br />External Tasks <br />External Milestone <br />Deadline <br />Progress <br />Manual Progress <br />US 101/Woodside I/C Improvement Project Schedule <br />Page 1 <br />Project: US101/Woodside I/C Im <br />Date: Mon 2/5/24