<br />Below is a list of the phases and the tasks included within each phase. Task Order No OO-l- 002 includes <br />Tasks for Phase 0 - Project Initiation and Tasks for Phase 1 Project Scoping. <br /> <br />Phase 0 - Project Initiation <br /> <br />Task 1 - Program Management Systems <br />Task 2 - Project and Administrative Record <br />Task 3 - Identification of Agencies and Experts <br />Task 4 - Environmental Section Outlines <br />Task 5 - Scoping Preparation <br /> <br />Phase 1 - Project Scoping - Preliminary Proiect Description <br /> <br />Task Q.1 - Develop Project Description and Purpose and Need Statement <br />Task Q.2 - Prepare Notice of Preparation (NOP) and Notice of Intent (NOI) <br />Task Q.3 - Circulate NOP/NOI <br />Task Q.4 - Conduct scoping meeting( s) <br />Task Q.5 - Manage and review scoping comments <br />Task Q.6 - Prepare Scoping Report to document comments and describe how each <br />shall be addressed <br />Task Q.7 - Define alternatives to be evaluated in EIR/EIS document Alternatives <br />Development Report <br />Task Q.8 - Identify Special studies and technical reports needed to support preparation of <br />the EIR/EIS <br />Task 9 Establish a scope of 'Nork and fee to provido services in Phase 2 <br />Task 10 Appro'/e contract amendment (City Council) <br /> <br />Phase 2 - Proiect ScoDina - Complete Proiect DescriDtion <br /> <br />Task 7.1 - Finalize Proiect Description <br />Task 7.2 - Prepare Notice of Preparation (NOP) and Notice of Intent (NOI) <br />Task 7.3 - Circulate NOP/NOI <br />Task 7.4 - Conduct scopinq meetinq(s) <br />Task 7.5 - Manaqe and review scopinq comments <br />Task 7.6 - Prepare Scopinq Report to document comments and describe how each shall be <br />addressed <br /> <br />Phase 2 ~ - Preparation of Draft Environmental Documents <br /> <br />Task ~.1 - Conduct special studies <br />Task ~.2 - Prepare Administrative Draft(s) EIR/EIS <br />Task ~.3 - Prepare Draft EIR/EIS <br />Task ~.4 - Circulate Draft EIR/EIS <br />Task ~.5 - Assemble and evaluate comments on Draft EIR/EIS <br />Task 6 Establish scope of work and foe to provide services in Phase J <br />Task 7 ,^.pprove contract amendment (City Counoil) <br /> <br />Phase 3 ~ - Preparation of Final Environmental Documents <br /> <br />Task ~.1 - Prepare responses to comments and text revisions if necessary <br />Task ~.2 - Prepare Administrative Draft(s) Final EIR/EIS <br />Task ~.3 - Prepare Final EIR/EIS <br /> <br />Phase 4 ~ - Consideration of Project Approval/Denial <br /> <br />Saltworks Environmental Program Task Order No. ()Q.1. 002 <br /> <br />Page 1 <br />