and tie -in to existing 1" service. reference Drawings 10.1 and 10.2.
<br /> DW No. 2: That portion of the work from Sta. 13 +01.85 to Sta. 20 +16.57, 174,138.00
<br /> including all butterfly valves, gate valves, air release valves, new fire hydrant
<br /> assemblies, and tie -in to existing fire service lateral. Reference Drawings 10.2 and
<br /> 10.3. End of Work for Phase 1 Sta. 20 +50.
<br /> Subtotal 382,026.00
<br /> Recycled Water Improvements: All labor, material and equipment pertaining Costs to
<br /> to the trenching and installation of the sanitary sewer pipes, manholes, and tie -ins to Complete
<br /> existing service laterals as detailed on the KPFF drawings 11.1, 11.2, 11.3, and 11.4 and
<br /> approved by the City of Redwood City, Engineering & Construction, on 14 October
<br /> 2009.
<br /> RW No. 1: That portion of the work from Sta. 20 +58.91 to Sta. 13 +33.58, 82,766.00
<br /> including all tees, gate valves, blow off valves, air release valves, and new service
<br /> lateral to One Marina. Reference Drawings No. 11.1 and 11.2.
<br /> RW No. 2: That portion of the work from Sta. 13 +33.58 to Sta. 20 +23.06, 69,238.00
<br /> including all air release valves, blow off valves, gate valves, meter box, and new
<br /> service laterals. Reference Drawings 11.2 and 11.3. End of Work for Phase 1 Sta.
<br /> 20 +50.
<br /> Subtotal 152,004.00
<br /> Concrete Improvements: All labor, material and equipment pertaining to the Costs to
<br /> demolition of existing concrete and the forming, placing, stripping of new concrete as Complete
<br /> detailed on the KPFF drawings 7.1, 7.2, 7.3, and 7.4 and approved by the City of
<br /> Redwood City, Engineering & Construction, on 14 October 2009.
<br /> Concrete No. 1: That portion of the work defined as all new curb, gutter, curb 135,371.00
<br /> cuts at filtration planters, truncated HC domes and driveway approaches.
<br /> Concrete No. 2: That portion of the work defined as the new round - about. 129,985.00
<br /> Concrete No. 3: That portion of the work new bicycle path. 77,149.00
<br /> Concrete No. 4: That portion of the work new sidewalk. 77,103.00
<br /> Subtotal 419,608.00
<br /> Roadway Improvements: All labor, material and equipment pertaining to the Costs to
<br /> demolition of existing AC paving and related base material and the excavation, Complete
<br /> grading, placement and compaction of new Class II AB base, new AC paving, new
<br /> striping and signage as detailed on the KPFF drawings 7.1, 7.2, 7.3, 7.4, 12.1, 12.2 and
<br /> 12.3 and approved by the City of Redwood City, Engineering & Construction, on 14
<br /> October 2009.
<br /> Roadway No. 1: That portion of the work defined as excavation, grading, 198,522.00
<br /> Class II AB base rock, AC paving for the entire roadway.
<br /> Roadway No. 2: That portion of the work defined as permanent striping and 17,285.00
<br /> signage,
<br /> Subtotal 215,807.00
<br /> Street Light & Pedestrian Light Improvements: All labor, material and Costs to
<br /> equipment pertaining to the demolition of existing street lights, installation of new Complete
<br /> street lights, new pedestrian lights, conduits, pull boxes, electrical conductors and
<br /> related appurtenances as detailed on KPFF drawings 16.1,16.2, and 16.3 and approved
<br /> by the City of Redwood City, Engineering & Construction, on 14 October 2009.
<br /> SL /PL No. 1: That portion of the work defined as demolition of existing street 72,724.00
<br /> lights, installation of new street lights and related pull boxes, conduit and electrical
<br /> conductor, and tie -in to existing service.
<br /> SL /PL No. 2: That portion of the work defined as new pedestrian lights and 88,884.00
<br /> related pull boxes, conduit and electrical conductor.
<br /> Subtotal 161,608.00
<br /> PG &E Gas & Electrical Improvements: All labor, material and equipment Costs to
<br /> B2 -3
<br />
|