No. 10.1.
<br /> GCR No. 2: Clearing & Grubbing 40,450.00
<br /> GCR No. 3: Construction of Detour Road, including Temporary Signage 94,554.00
<br /> & Striping
<br /> GCR No. 4: Demolition and Removal of Detour Road, including 31,518.00
<br /> Temporary Signage & Striping
<br /> Subtotal 166,522.00
<br /> DISCRETE COMPONENTS:
<br /> Storm Drainage Improvements: All labor, material and equipment pertaining Costs to
<br /> to the trenching and installation of the storm drainage pipes,° Manholes, tie-ins to Complete
<br /> existing inlets `and service laterals, tie -In to the existing storm water pump
<br /> station and tie -ins to the infiltration galleries ° as detailed one' =the KI'F drawings 8.1,
<br /> and 4,3 and approved by the City of .Redwood City, Engineering ' Construction,
<br /> on 14 October 2
<br /> SD No. 1: That portion of the work at the tie -in to the existing storm water lift 65,960.00
<br /> station at storm drain manhole #13 to storm drain manhole #10, including tie -in to
<br /> the existing drain inlet. Reference Drawing No. 8.1.
<br /> SD No. 2: That portion of the work from storm drain manhole #10 to storm 32,284.00
<br /> drain manhole #9, including tie -in to the existing drain inlet. Reference Drawings No.
<br /> 8.1 and 8.2.
<br /> SD No. 3: That portion of the work from storm drain manhole #9 to storm 53,793.00
<br /> drain manhole #6, including tie -in to the existing drain inlet. Reference Drawing No.
<br /> 8.2.
<br /> SD No. 4: That portion of the work from storm drain manhole #6 to storm 63,085.00
<br /> drain manhole #3, including tie -in to the existing drain inlet and existing service
<br /> lateral. Reference Drawings No. 8.2 and 8.3. End of Work for Phase 1 Sta. 20 +50.
<br /> SD No. 5: That portion of the work at the round -about to connect the 8,590.00
<br /> landscape drainage and infiltration galleries to the new storm drainage system.
<br /> Reference Drawing No. 8.1.
<br /> Subtotal 223,712.00
<br /> Sanitary Sewer Improvements: All labor, material and equipmentpertaining Costs to
<br /> to the trenching and installation of the sanitary sewer pipes, manholes, and tie -ins to Complete
<br /> existing service laterals as detailed on the KPH drawings 9.1, 9.2, 9.3 -and 9.4 and
<br /> approved by the City of Redwood City, Engineering & Construction, on 14 October
<br /> 2009'
<br /> SS No. 1: That portion of the work from the tie -in to existing manhole 64,184.00
<br /> sanitary sewer manhole #3, including new service lateral and sanitary sewer
<br /> manhole #3A. Reference Drawings 9.1 and 9.2.
<br /> SS No. 2: That portion of the work from sanitary sewer manhole #3 to 52,371.00
<br /> sanitary sewer manhole #5, including tie -in to existing service lateral. Reference
<br /> Drawing 9.2.
<br /> SS No. 3: That portion of the work from sanitary sewer manhole #5 to 35,998.00
<br /> sanitary sewer manhole #7, including tie -in to existing service lateral. Reference
<br /> Drawings No. 9.2 and 9.3. End of Work for Phase 1 Sta. 20 +50.
<br /> Subtotal 152,553.00
<br /> Domestic Water Improvements: All labor, material and equipment pertaining C osts to .
<br /> to the trenching and installation of the sanitary sewer pipes, manholes and tie -ins to Complete
<br /> existing service Laterals as detailed on the ICPk"P drawings .1,10.2,10.3,1l?*4 and 10.
<br /> and approved by ,the City of Redwood City, Engineering & Construction, on 14
<br /> October 21109.
<br /> DW No. 1: That portion of the work from Sta. 21 +41.47 to Sta. 13 +01.85, 208,014.00
<br /> including all tees, butterfly valves, air release valves, blow off valves, new fire •
<br /> B2 -2