Exhibit A <br /> <br />Fifth Avenue Pump Station <br />Final Design <br /> Scope of Work <br /> <br />Work Item <br /> <br />Fcc <br /> <br />Scheduled <br />Completion <br /> <br />Task 1 - Design Development <br /> <br />Task 2 - Construction Documents Preparation - <br />35% Design Phase <br /> <br />Task 3 - Construction Documents Preparation - <br />65% Design Phase <br /> <br />Task 4 - Construction Documents Preparation - <br />95% Design Phase <br /> <br />Task 5 - Construction Documents Preparation - <br />100% Design Phase <br /> <br /> Design Subtotal <br /> Reimbursable Budget <br /> <br /> Total Design Budget <br /> <br />$9,162 <br /> <br />69,742 <br /> <br />86,267 <br /> <br />70,568 <br /> <br /> 20,128 <br /> <br />$255,867 <br /> <br /> 10,000 <br />$265,867 <br /> <br />March, 30 2003 <br />June 30, 2003 <br /> <br />August 15, 2003 <br />October 15, 2003 <br /> <br /> November 30, <br /> 2003 <br /> <br /> <br />