6.2.A. - Page 1 <br />REPORT <br />To the Honorable Mayor and City Council <br />From the City Manager <br />July 11, 2011 <br />SUBJECT <br />Final Acceptance —Woodside Road Median Improvements at El Camino Real <br />RECOMMENDATION <br />Accept, by motion, the Woodside Road Median Improvements at El Camino Real, and <br />authorize the release of bonds and the retention according to city procedures. <br />BACKGROUND <br />On February 7, 2011, Council awarded the construction contract for the Woodside Road <br />Off -ramp Median Landscaping at El Camino Real to Scapes, Inc. of Half Moon Bay. <br />The project was awarded for a base bid of $63,420.00. Construction began in April, <br />2011, substantial completion was achieved by May, 2011, and final completion in June, <br />2011. The project is successfully completed in accordance with the plans and <br />specifications. One (1) change order for $755.00 was issued to remove a pedestrian <br />safety hazard and additional tree. The final contract amount is $64,175.00, which is <br />1.2% more than the contract amount initially awarded. <br />The Woodside Road Median Improvements at El Camino Real were proposed as the <br />first in a series of projects to improve the aesthetics of the Woodside Road corridor. The <br />project site is a ±54,500 square foot landscape area adjacent to the southbound off - <br />ramp on Woodside Road at El Camino Real. This site was originally full of overgrown <br />vegetation, trash, and weeds; it had become a retreat for transients. Cleaning up this <br />area created a safer, more inviting environment for area residents and visitors to <br />Redwood City. Staff will return to Council in the near future to present <br />recommendations for other projects to enhance Woodside Road. <br />ALTERNATIVES <br />Council may choose not to accept the project or authorize the release of bonds and <br />retention which would be contrary to the terms of the contract, prior Council action, and <br />public contracting code. <br />FISCAL IMPACT <br />Sufficient funding for the work of this project was previously approved and appropriated <br />as Gas Tax Construction Fund — Woodside Road Widening Landscape. <br />ENVIRONMENTAL REVIEW <br />Not applicable to this report <br />