7.A. - Page 207 <br /> 13. Submission — Construction Document Excavation, shoring, waterproofing and <br /> packa�e to City. The Developer shall foundation: by July 1, 2013 <br /> prepare and submit to the City for review <br /> and approval a complete Construction Superstructure, concrete and steel: by July 15, <br /> Document package. 2013 <br /> All remaining Construction Documents: By <br /> August 20, 2013 <br /> 14. A�roval of Construction Documents. Excavation, shoring, waterproofing and <br /> City shall approve or disapprove foundation: by August 20, 2013 <br /> Developer's Construction Documents. <br /> Superstructure, concrete and steel: by <br /> September 15, 2013 <br /> All remaining Construction Documents: By <br /> October 15, 2013 <br /> 15. A�roval of Final Map A�lication. Prior to the close of escrow. <br /> Developer shall submit to City a <br /> completed final parcel map application. <br /> 16. Close of Escrow. The City shall convey Upon the satisfaction of the conditions and <br /> title to the City Property to the within the time period set forth in Section 3 of <br /> Developer, and the Developer shall this Agreement. <br /> acceptsuch conveyance. <br /> 17. Recordation of Final Parcel Map for Site. Immediately upon the close of escrow and <br /> The Developer shall record the approved prior to issuance of first building permit.. <br /> Final Parcel Map for the Site. <br /> 18. Submission — Certificates of Insurance Prior to the date set forth herein for the <br /> The Developer shall furnish to the City commencement of construction of the <br /> duplicate originals or appropriate Developer's improvements on the Site. <br /> certificates of bodily injury and property <br /> damage insurance policies. <br /> 19. Governmental Permits. The Developer Prior to the date set forth herein for the <br /> shall obtain any and all permits required commencement of construction of the <br /> by the City or any other governmental Developer's improvements on the Site. <br /> City. <br /> 20. Commencement of Construction of Within 30 days after issuance of excavation, <br /> Developer's Improvements. The shoring, waterproofing and foundation permit. <br /> Developer shall commence excavation, <br /> shoring, waterproofing and foundation <br /> work at the Site. <br /> E�ibit "D" <br /> Performance Schedule <br /> Page 3 <br /> 82483.00009\7571312.11 <br /> ATTY/AGR/2013.118/BLOCK 2 HUNTER STORM <br /> REV: 07-19-13 PT <br />