Proposed Project Schedule (if all funding is available): <br /> 2014 2015 2016 2017 2018 2019 2020 2021 2022 <br /> Project Study 6/06 <br /> Report <br /> Alts Analysis 10/11 <br /> Environmental <br /> Project Approval 1f14- 12/15 <br /> Design 6/16-6/18 <br /> Right-of-Way You - 4/17-9/18 <br /> Construction are 4/19- 12/21 <br /> here <br /> Proposed Environmental Schedule: <br /> 1/14 4/14 7/14 10/14 1/15 4/15 7/15 10/15 1/16 <br /> Alternatives Investigation 1/14- 4/14 <br /> Technical Studies 4/14- 11/14 <br /> Preferred Alternatives 6/14- 12/14 <br /> Draft Environmental Document 7/14- 2/15 <br /> Public Circulation IM 2/15-3/15 <br /> ~ k Final Environmental Document 3/1 -- 12/15 <br /> -Redwood Project Approval *12/15 <br /> IGIN CBolnf UI <br /> -f._.{ . \ lat lit i 14:4:2 <br />