_. _ �� . �.,�.: .��,��. <br /> Products <br /> • Planning Commission Recommended Draft Planned Development Permit Regulations <br /> • Final Planned Development Permit Regulations <br /> SCHEDULE <br /> Task 1 Tasks A-D complete within six weeks of execution. Task E ongoing. <br /> Task 2 Tasks A and B complete within 4 weeks of Task 1 D. <br /> Task 3 Tasks A and B complete within 6 weeks of Task 2B. <br /> Task 4 Task A and B complete within 8 weeks of Task 2B. <br /> Task 5 Task A, B and C complete within 8 weeks of Task 4B. <br /> Additional Services—As negotiated. <br /> COMPENSATION <br /> Task 1 $5,225 <br /> Task 2 $6,600 <br /> Task 3 $7,870 <br /> Task 4 $7,870 <br /> Task 5 $7,250 <br /> Total $34,815 <br /> ATTY/AGR/2014.071/DYETT&BHATIA <br /> REV:05-28-14 VR <br /> Page 12 of 12 <br />