7.1.D. - Page 9 <br /> established a safety program, that the safety program established by the <br /> Contractor is in compliance with applicable law, rule or regulation and that <br /> the Contractor has implemented its safety program. <br /> g. CM shall promptly notify the CITY in writing of all CM observed instances of <br /> Contractor's failure to comply with applicable safety requirements. If in the <br /> course of performing services during the construction, the CM observes a <br /> safety violation or other unsafe condition on or about the site or surrounding <br /> area which have an immediate or potential or actual adverse effect on life or <br /> property, the CM is authorized, without prior notice to the CITY or prior <br /> directive by the CITY, to take all actions deemed necessary and appropriate <br /> by the CM under the then existing circumstances to prevent such actual or <br /> potential adverse effect. <br /> h. CM shall become familiar with all CEQA documents and permit requirements <br /> from other agencies having jurisdictions over the site or work that will affect the <br /> project and the construction site. CM shall be responsible for monitoring all <br /> aspects of the project as it relates to the requirements. CM shall monitor the <br /> Contractor's compliance with all requirements of the CEQA documents and <br /> permits by other agencies. CM shall take prompt action appropriate under the <br /> circumstances, including stopping the work and thereupon notifying the CITY in <br /> writing if Contractor is not following all requirements. <br /> 6. Contract Change Order (CCO) processing, CM services shall include but are not <br /> limited to the following: <br /> a. Coordinate and disseminate correspondence, drawings and other written <br /> materials by and between the Contractor, the CITY and the design consultants <br /> relating to changes to the project. CM will coordinate the Contractor's <br /> performance of changes authorized by the CITY. CM shall maintain a log or <br /> other written records to monitor the pendency and disposition of change and <br /> CCOs to keep the CITY advised of the status of the same and the actual or <br /> potential impact of any particular change or CCO or the cumulative effects <br /> thereof on the construction cost or time for completion of construction of the <br /> project. <br /> b. Assist the CITY and design consultant in evaluation of requests for the <br /> Contactor for issuance of CCOs, assist in negotiations with the Contractor <br /> relative to the CCOs proposals and the adjustment of the contract price or the <br /> contract time under the construction contract. CM will make recommendations <br /> to the CITY and the design consultant for handling and disposition of the <br /> Contractor's proposal relative to the changes. If a change to the construction <br /> contract is approved or authorized by the CITY, CM will assist the CITY and <br /> the design consultant in the preparation of a CCO reflecting such approved or <br /> authorized change to the construction contract. The CM is not authorized, <br /> without the prior consent and approval of the CITY, to effectuate or authorize <br /> any change to the work of the project. The CM shall be liable to the CITY for <br /> all direct and consequential costs, losses or damage resulting from the CM's <br /> direction or authorization to effectuate a change to the work of the project <br /> without the prior direction and authorization by the CITY. <br /> 7. Claims handling, CM service shall include but are not limited to the following: <br /> a. Assist the design consultant in the review, evaluation and processing of claims <br /> asserted by the Contractor; CM will make recommendations to the CITY as to <br /> REV:04-06-15 MIL <br /> Page 7 of 10 <br /> ATTY/AGR.Amend No. 1/Gilbane Building Company <br />