Schedule <br /> The estimated schedule to complete this work is summarized below, with relative <br /> completion weeks based on receipt of formal Notice to Proceed from City. <br /> TASK DURATION DUE END OF WEEK <br /> 1 Pre-Study Meeting 1 working day 1 <br /> 2 VA Study 5 working days 2 <br /> 3 VA Preliminary Report 10 working days 4 <br /> Review 5 working days 5 <br /> 4 Implementation Meeting 1 working day 6 <br /> 4 Implementation Action Memo 10 working days 8 <br /> OR <br /> 4 Final Value Analysis Study Report 10 working days 8 <br /> If both VA lmp/ementation Action Memorandum and Fina/ Value Ana/ysis Study Report <br /> are required, 10 additional working days will be added to the schedule. <br /> REV:04-15-15 VR <br /> Page 12 of 15 <br /> ATTY/AGR2015.065Nalue Management Strategies, Inc. <br />