ATTY/AGR/2016.206/JPB – CALTRAIN ELECTRIFICATION   <br />REV: 07‐26‐16 VR  <br />Page 5 of 14  <br />C. Specific to the City of Redwood City, and based on preliminary design, the <br />Project elements anticipated within City of Redwood City, include: <br />(1) OCS poles. Installation of foundations, poles and appurtenances. <br />(2) Stringing wire for OCS. Which will require temporary street closures when work <br />occurs at an existing at-grade crossing. Specificity about the closures will be <br />included in the Traffic Control Plan. <br />(3) Construction of TPF located between MP 26.2 – 26.3 and is east of State Route <br />84 and the Right-of-Way (ROW). The location of this TPF is shown in Exhibit A <br />as "SWS-1". <br />(4) Staging areas. The PCEP FEIR identified one potential staging area for the DB <br />Contractor's use. The location of this staging area is east of State Route 84 and <br />the Right-of-Way (ROW) between MP 26.2 – 26.4. This location is shown in <br />Exhibit B. Additional staging areas will comply with applicable mitigation <br />measures and will be coordinated with the City of Redwood City. <br />SECTION 5: GENERAL COMMITMENTS <br /> <br />A. The JPB will avoid affecting any City Improvements to the extent feasible. In the <br />event a City Improvement requires modification and/or relocation, JPB shall be responsible for <br />the design and construction of the City Improvement, subject to review and approval by the City. <br />A comprehensive list of affected City Improvements will be prepared by the JPB, and will be <br />provided to the City for review. The City agrees to cooperate with the JPB in the JPB’s <br />preparation of such list to identify all City Improvements affected by the Project. Any <br />replacement City Improvements will be of a similar kind and capacity to the existing facilities <br />and compliant with existing City codes and standards. If City desires to increase or upgrade a <br />City Improvement beyond its existing City codes and standards, it shall be responsible for any <br />additional costs for that change. Existing City codes and standards shall be applied such that any <br />replacement of City Improvements shall be of a size, material and specification meeting codes <br />and standards in effect at the time of City’s review and approval. Specifically, replacement City <br />Improvements shall be of the minimum size, standard material, and specification as if new, <br />except where meeting such size, material or other specification is waived by the City. The <br />Parties will agree to a protocol for the review of plans and the inspection of affected City <br />Improvements. The City has provided, and JPB has received, the document titled “Redwood <br />City Preliminary Utility Information Regarding PCEP” (Exhibit D). <br />B. In order to minimize disruption to the Caltrain passenger service during project <br />construction as well as maximize protection of people and property, most of the Project work <br />will be performed outside of the weekday peak commute hours. <br />C. The JPB will provide the City with plan(s) addressing haul routes along city <br />streets and roadways, and any staging areas or property owned or controlled by the City for City <br />review and approval, which approval shall not be unreasonably withheld. JPB will document <br />existing conditions by video and photographic record of the proposed and accepted haul routes <br />6.1.A. - Page 8