responsibility of each agency for the Bus Shelter maintenance. This is the first <br />partnership established among SamTrans, Local Government, and the Community. <br /> <br />The total cost of the project was $39,346.00. The construction was inspected by <br />Assistant Civil Engineer Paul Willis. There were no Change Orders issued for this <br />project, and all work was completed in conformance with the plans and specifications, <br />and to the satisfaction of the City's Engineering & Construction office. <br /> <br />Fiscal Impacts <br />Funds in the amount of $45,000.00 are appropriated in the FY 2000-2001 GID 1-64 <br />Capital Improvement Program budget for the Redwood Shores Bus Shelter Installation <br /> <br />Chu Chang ~//Manager'/~el'Patte~n°;i Ed Everett <br />Senior Civil Engineer neering & Construction City Manager <br /> <br />JP/CHU:ss <br />s/library/reports/chu/Accept_Redwood Shores Bus Shelter <br /> <br /> <br />