Laserfiche WebLink
<br /> --. <br />Brian Lee <br />January 22, 1997 <br />Page 2 <br />Tasks - Schedule <br />A list of tasks with a tentative schedule (dependent upon the companies review time) is as <br />follows: <br /> Completed by <br />Task I - Prepare Initial Plans February 18, 1997 <br />Task 2 - Coord. Mtg. February 25, 1997 <br />Task 3 - Final Plans March 10, 1997 <br />Task 4 - Specifications March 10, 1997 <br />Task 5 - Estimate March 10, 1997 <br />With a one week review time for both initial and final plans, the construction contract PS&E <br />could be provided to the City by the end of March. <br />Cost <br />The cost for this work is shown on the attached spreadsheet. <br />Very truly yours, <br />cc: Ron T. Calhoun <br /> Andrew P. Yeung <br /> Page 2 of 3 <br /> D:IWPWlN60IWPDOCSIPRODUCTIlFCJìUTILITY,WPD <br />'___n, ¡ <br />