Laserfiche WebLink
Schedule <br />Page 24 of 26 <br />REV: 11-08-17 PR <br />ATTY/AGR.2017.262/ESA / Harbor View Project <br />Notice to Proceed <br />November 27, 2017 <br />Contract Agreement with the City <br />December 4, 2017 <br />Kick -Off Meeting <br />Week of December 4,2017 <br />c <br />ESA Prepares Preliminary Project Description, NOP, and <br />Mid December <br />2 weeks <br />m <br />Scoping Meeting Presentation <br />City Review (2 weeks) <br />Mid — Late December <br />2 weeks <br />Y <br />u <br />Y <br />Publish NOP <br />January 5, 2018 <br />30 -day Scoping Period <br />January 8- February 7 <br />30 days <br />Scoping Meeting - City Council <br />January TBD <br />Conduct Traffic Counts (Fehr & Peers) <br />Mid -Late January <br />0 <br />m <br />Draft Transportation Impact Analysis (TIA) (F&P) <br />' Early Feb •Early May <br />5 months <br />oa <br />City Review (4 weeks) <br />Late May -Eady June <br />4 weeks <br />N <br />Revised TIA Inputs and Assumptions for EIR(F&P) <br />Late June —Eady July <br />3weeks <br />F <br />Traffic input for EIR Alternatives (F&P) <br />Mid July <br />1 week <br />Prepare/Submit Administrative Draft EIR #1 (ESA) <br />FebJulya <br />6 months <br />City Review (4 weeks) <br />August �4 <br />weeks <br />W <br />Prepare/Submit Administrative Draft EIR #2(ESA) <br />Early September 12 <br />weeks <br />w <br />City Review (3 weeks) <br />Late September- I3 <br />weeks <br />Prepare/Submit Screencheck Draft EIR (ESA) <br />Early October <br />1 week <br />City Review (2 weeks) <br />! Mid October <br />2 weeks <br />Finalize/ Publish Draft EIR <br />Mid -November <br />1 week <br />u <br />a 2 <br />45 -day ay Public Review and Comment Period <br />November to Late <br />5 days <br />> <br />Public Hearing on the Draft EIR <br />Late November or Early <br />December Hearing <br />weeks <br />Prepare/Submit Administrative Response to December—Mid <br />Comments/Final EIR #1 (ESA) <br />I January <br />c <br />City Review (3 weeks) <br />Late January <br />3 weeks <br />PreparelSubmit Administrative Response to <br />Early February <br />3 weeks <br />Comments/Final EIR #2 <br />V <br />City Review (2 weeks) <br />Late February <br />2 weeks <br />Prepare/Submit Screencheck Response to <br />- Early March <br />2 weeks <br />M <br />Comments/Final EIR (ESA) <br />1 <br />c <br />City Review (2 weeks) <br />MidMarch <br />2 weeks <br />LL <br />Release Final EIR <br />Late March <br />Certification Hearings <br />April 2019 <br />a Assumes confirmation of all traffic assumptions at least two weeks prior to submittal ofADEIR #1. <br />Six (6) weeks after end of the public comment period, which assumes <br />a moderate number of public comments and <br />effort to resbond (150 labor hours Der this scone of work Task 6). <br />Page 24 of 26 <br />REV: 11-08-17 PR <br />ATTY/AGR.2017.262/ESA / Harbor View Project <br />