Redwood City Sanitary Sewer Master Plan Executive Summary
<br /> FINAL
<br />
<br />August 2008 5
<br />Recommended Capacity Improvement Program
<br />The Capital Improvement Program (CIP) recommended in this study is designed to provide adequate
<br />sewer system capacity for the City’s existing and anticipated future development. The total estimated
<br />capital cost of the CIP is approximately $38 million, as shown in Table ES-1. These cost estimates
<br />include baseline construction costs for gravity trunk sewers using open-cut and trenchless methods, lower
<br />lateral replacement for remove-and-replace projects, and cost allowances for project mobilization and
<br />demobilization, traffic control, and bypass pumping. An additional cost allowance for robust shoring of
<br />trenches (e.g., interlocking sheet piles) was added for projects located near the San Francisco Bay, as
<br />these projects are likely to be affected by poor (bay mud) soil conditions. The total estimated capital
<br />costs also include a 30 percent allowance for contingencies for unknown conditions and an allowance of
<br />30 percent of construction cost for engineering, administration, and legal costs. The estimated costs are
<br />considered planning or conceptual level estimates and are considered to have an estimated accuracy range
<br />of -30 to +50 percent, suitable for budget planning purposes.
<br />
<br />Table ES-1 Capacity Projects and Costs, Ordered by Priority
<br />Project
<br />ID
<br />Location Description Priority
<br />Rank
<br />Flow Conf.
<br />Level
<br />Cost
<br />08b Manzanita St north of El Camino,
<br />under railroad
<br />1,700 feet of 18 inch pipe 1 1 $ 2,720,000
<br />11 El Camino Real, Maple St, Main St 3,300 feet of 15 inch pipe 1 1 $ 2,360,000
<br />07 Palm Ave between Kentfield Ave
<br />and Hudson St
<br />2,300 feet of 12 to 15
<br />inch pipe
<br />1 2 $ 1,150,000
<br />10 James Ave, California St, Marshall
<br />St, Jefferson Ave, Bradford St,
<br />Walnut St
<br />4,400 feet of 15 to 33
<br />inch pipe
<br />1 2-3 $ 7,940,000
<br />05a Along Truman Ave to MacGarvey
<br />Ave to Fairview Ave to Roosevelt
<br />Ave, ending at Roosevelt Ave and
<br />Junipero Ave
<br />2,100 feet of 15 to 21
<br />inch pipe
<br />2 2 $ 1,110,000
<br />12 Lincoln Ave, Beech St, Stambaugh
<br />St, Walnut St,
<br />5,700 feet of 27 to 30
<br />inch pipe
<br />2 3 $ 4,910,000
<br />04 Brewster Ave between Clinton St
<br />and Arch St
<br />600 feet of 15 inch pipe 3 2 $ 330,000
<br />01 Edgewood Rd between Yorkshire
<br />Ln and Alameda de las Pulgas
<br />200 feet of 12 inch pipe 3 3 $ 90,000
<br />03 Winslow St from Whipple Ave to
<br />Brewster St. Brewster St between
<br />Winslow St and Veterans Blvd2
<br />2,000 feet of 18 inch pipe 3 3 $ 3,550,000
<br />06 Roosevelt Ave from Connecticut
<br />Dr to Upton St2
<br />1,600 feet of 10 inch pipe 3 3 $ 680,000
<br />08a Adjacent to Woodside Rd, south of
<br />El Camino Real
<br />1,000 feet of 12 to 15
<br />inch pipe
<br />3 3 $ 2,220,000
<br />08c Heller St from Manzanita to
<br />Chestnut, Chestnut St to Broadway
<br />3,400 feet of 18 to 21
<br />inch pipe
<br />3 3 $ 3,200,000
<br />09 El Camino Real from Center St to
<br />Manzanita St
<br />1,300 feet of 10 inch pipe 3 3 $ 720,000
<br />05b Roosevelt Ave between Junipero
<br />Ave and Hudson St
<br />2,800 feet of 24 inch pipe 4 2 $ 1,690,000
<br />02 Whipple Ave between Arguello St
<br />and Warren Ave
<br />400 feet of 12 inch pipe 4 3 $ 190,000
<br />13 Walnut St to Maple PS 1,400 feet of 54 inch pipe 4 3 $ 4,950,000
<br />Total $37,810,000
<br />6.2.A. - Page 221
|