6.A. - Page 1 of 4 <br />/<�ik <br />Redwood <br />CitylCallifornia <br />Faunded 1867 <br />A,&/ <br />DATE: September 21, 2020 <br />SUBJECT <br />STAFF REPORT <br />To the Honorable Mayor and City Council <br />From the City Manager <br />Award - 2019-2020 Watermain Replacement Project - Arlington Neighborhood (Edgewater Park) <br />RECOMMENDATION <br />By motion, approve and authorize the City Manager to execute the contract documents and award the <br />standard form contract for the 2019-2020 Watermain Replacement Project - Arlington Neighborhood to <br />Casey Construction, Inc. of Emerald Hills CA for their responsive and responsible low total bid of <br />$1,479,195.00 and authorize the City Manager or the City Manager's designees to increase the contract <br />amount, if necessary, up to 10% of the amount awarded, in an amount not to exceed $1,627,114.50 and <br />find that the project is exempt from the requirements of the California Environmental Quality Act (CEQA) <br />under CEQA Guidelines Section 15302 (Replacement or Reconstruction). <br />STRATEGIC PLAN GUIDING PRINCIPLE <br />Public Safety <br />BACKGROUND <br />On October 24, 2011, the City Council accepted the Water System Master Plan Report and directed staff <br />to move forward with specific capital improvement projects and programs for future Council <br />consideration. The Water System Master Plan prioritized the system pipeline replacement into seven <br />priorities or programs to improve the reliability of the system and provide improved fire protection. <br />Priority -One Pipeline Replacement Projects are completed. Staff is working to complete all Priority -Two <br />Pipeline Replacement Projects, which focus on the replacements of mainly aging metal pipelines with 4 - <br />inch or less in diameters. <br />Page 1 of 3 <br />City of Redwood City 1017 Middlefield Road, Redwood City, CA. 94063 Tel: 650-780-7000 www.redwoodcity.ore <br />11 <br />