Exhibit "A"
<br />Change Order No. 2
<br />CITY OF REDWOOD CITY, CALIFORNIA
<br />COMMUNITY DEVELOPMENT DEPARTMENT
<br />ENGINEERING & TRANSPORTATION
<br />Sheet: 1 of
<br />Date: February 8th, 2021
<br />Project: Marshall Street Intersection Improvements at
<br />Jefferson Avenue and Middlefield Road
<br />Contractor: Seton Pacific Construction
<br />CHANGE ORDER NO:
<br />PURCHASE ORDER NO:
<br />ACCT. NO:
<br />2
<br />51226
<br />264-85085
<br />Original Contract Amount: $398,805.00
<br />Previous Change Orders: $7,499.00
<br />This Change Order:
<br />264-85085
<br />$71,893.14
<br />Accumulative Total: $478,197.14
<br />You are hereby directed to make the herein described changes from the plans and specifications or do the following described
<br />work not included in the plans and specifications of this contract. All new work herein described shall be done in accordance
<br />with the applicable provisions of the plans and specifications, except as specifically modified by this contract change order.
<br />NOTE: This change order is not effective until approved by the City. This change order includes all costs and time required to
<br />complete the additional work described herein and the contractor shall be entitled to no other compensation.
<br />DESCRIPTION OF CHANGE COST
<br />At the intersection of Jefferson Avenue and Marshall Street:
<br />With the exception of asphalt concrete, the contractor shall provide all labor,
<br />equipment, material, and incidentals to reconstruct the intersection of Marshall
<br />Street and Jefferson Avenue, complete in place for a lump sum cost of
<br />$222,223.14. The contractor's scope of work explicitly includes but is not limited
<br />to the following:
<br />a. The contractor shall be responsible for all traffic control associated with
<br />this work
<br />b. The contractor shall be responsible for lowering the lids/rims of all utilities
<br />within the work area to grades shown on the project plans
<br />c. The contractor shall be responsible for sawcutting, demolishing, off
<br />hauling, and dumping the existing pavement as needed to meet the
<br />grades specified by on Sheet 6 of the project plans while providing a
<br />minimum 9" thick asphalt concrete section within the intersection
<br />d. The City will be purchasing the asphalt concrete from Granite Rock
<br />e. The contractor shall be responsible for installing a 9" thick deeplift of
<br />asphalt concrete within the limits of work shown on the project plans,
<br />complete in place
<br />f. The contractor shall be responsible for completing all remaining traffic
<br />signal modification work as shown on the project plans and project
<br />specification
<br />g. The contractor shall be responsible for completing all signing and striping
<br />work as shown on the project plans and project specification
<br />h. The field modified striping changes
<br />$222,223.14
<br />The following bid items are delted from the project at the bid price:
<br />a. Bid item #1, Mobilization, Notification, and Incidentals, 0.1 LS,
<br />$55,000.00/1-S
<br />($5,500.00)
<br />b. Bid item #2, Water Pollution Control Program, 0.25 LS, $10,000.00/1-S
<br />($2,500.00)
<br />c. Bid item #3, Traffic Control, 0.2 LS, $25,000.00/1-S
<br />($5,000.00)
<br />d. Bid Item #6, Cold Plane Asphalt Concrete Pavement, 7665 SQFT,
<br />$2.00/SQFT
<br />($15,330.00)
<br />e. Bid Item #9, Remove Drainage Inlet, 1 EA, $500.00 EA
<br />($500.00)
<br />f. Bid Item #10, Hot Mix Asphalt, 100 TON, $360.00/TON
<br />($36,000.00)
<br />g. Bid Item #15, Curb Inlet D-1, 1 EA, $5,000.00 EA
<br />($5,000.00)
<br />h. Bid Item #16, Adjust Utility Rims to Grade, 8 EA, $250.00 EA
<br />($2,000.00)
<br />i. Bid item #17, Traffic Signal Modification (Jefferson and Marshall), 0.6 LS,
<br />$65,000.00/1-S
<br />($39,000.00)