<br />6.10
<br />Page 2
<br />
<br />5. Customer site retrofits for each existing private or public site with a landscape
<br />irrigation meter. Retrofits will occur as each property owner ag rees to convert to
<br />recycled water for landscape irrigation and industrial uses.
<br />Status: Retrofit Bid Package 1 (18 commercial sites in the Redwood Shores area)
<br />was 1000/0 constructed in time to meet the demands of the 2007 irrigation season.
<br />Retrofit Bid Package 2 is 95% completed and is scheduled for full completion in time
<br />to meet the demands of the 2008 irrigation season.
<br />
<br />Bid Package 8 (see attached map) is the ninth distribution pipeline construction project.
<br />The work of this project will connect the transmission piping system in the Redwood
<br />Shores area to the transmission piping system in the Seaport area and completes
<br />Phase I of the Recycled Water transmission piping system to potentially serve all
<br />Redwood City customers east of Highway 101. Piping will be extended along East
<br />Bayshore Road, Bair Island Road, Redwood Creek, Highway 101, and Maple Street to
<br />deliver recycled water to the Seaport area. More than 1,840 linear feet of PVC
<br />(Polyvinyl Chloride) and welded steel pipe, 24 inches in diameter, will be constructed in
<br />approximately five months.
<br />
<br />The 16 bids received at the bid opening on January 21,2009, are summarized below:
<br />
<br /> Bidder Bid Amount
<br />Peak Engineering Inc., San Francisco $ 949 450.00
<br />Rodan Builders Inc., Belmont 983,800.00
<br />Synergy Project Management Inc., San Francisco 1,185,326.49
<br />California TrenchJess Jnc., HayWard 1,196,600.00
<br />Delta Excavating Inc., Antioch 1,206,920.00
<br />Ranger Pipelines Inc., San Francisco 1,216,628.00
<br />Con-Quest Contractors Inc., San Francisco 1,326,710.00
<br />J & M Inc., Livermore 1,327,466.00
<br />Pacific Underground Construction Inc.,San Jose 1,340,050.00
<br />JMB Construction Inc., South San Francisco 1,341,625.00
<br />D.W. Young Construction Company Inc., Alamo 1,357,900.00
<br />North Bay Construction Inc., Petaluma 1,394,176.00
<br />Mountain Cascade Inc., Livermore 1,447,295.00
<br />Preston Pioelines Inc.. MilDitas 1,485,877.00
<br />Sanco Pipelines Inc., Campbell 1,498,010.00
<br />K.J. Woods Construction Inc., San Francisco 1,608,000.00
<br />Engin;eef's Estima.te ......... ............ ............ -.. $1,550,000.00..... - .... ...... ..
<br />... . . ...... ...,'.. ..... . .... ... ... -
<br />Recommended Bidder: Peak Engineering, Inc.
<br />Substantiation: Peak Engineeringr Inc., of San Francisco is the lowest responsive and responsible
<br />bidder.
<br /> I
<br />
<br />The low bid of $949,450.00 from Peak Engineering, Inc., is 38% lower than the
<br />Engineer's estimate of $1,550,000.00 for the cost of construction. Based upon the bids
<br />received, staff believes that the low bid of $949,450.00 is reasonable and responsive,
<br />and recommends awarding the contract to Peak Engineering, Inc.