Laserfiche WebLink
6.A. - Page 19 of 24 <br />Change Complexity Classification: ® High <br />❑ Medium <br />❑ Low <br />Description.. <br />Extend Phase 1 Go Live to July 2021 <br />$344,880.00 <br />Extend Phase 2 Go Live to January 2022 <br />$452,550.00 <br />Total <br />$797,430.00 <br />The detailed payment schedule may be found in Appendix B of this document. <br />IMPACT TO SCOPE OF SERVICES <br />Resource Impact: The City and CherryRoad resources will be staffed according to the revised <br />staffing plans in Appendix A (SOW Sections 4.2.1 and 4.2.2) <br />Scope Impact: There is no change in project scope. <br />Budget Impact: This Change Order #2 includes a net contract and budgetary increase of <br />$797,430.00. <br />Timeline Impact: The Phase 1 Financials Go Live date will be July 2021 and Phase 2 HCM Go <br />Live date will be January 2022. <br />REV: 03-25-2021 PR <br />[The remainder of this page left intentionally blank] <br />ATTY/AGR.2021/Amend No. 2/CherryRoad (Page 8 of 13) <br />W <br />