Laserfiche WebLink
17060 P a g e | 12 <br />Proposal for Storm Drain Pump Station Improvements Projects <br />BRADFORD PUMP STATION <br />12. Design submittals to include Basis of Design Report, 60%, 90%, and final design submittals. BODR to include <br />conceptual 1-line diagram and electrical equipment elevation. BODR will also include I&C and Electrical <br />design criteria to be applied to the Project. <br />13. Attendance at the Project Kickoff meeting is not required. <br />14. Participation in a maximum of four design workshops is included. Workshop is assumed via <br />teleconferencing. Physical attendance will not be required. <br />15. Assistance during bidding is included with Bidding Phase Services. However, attendance at pre-bid site <br />meetings will not be required. Conformed drawings following the bidding period will not be required. <br />16. O&M manuals will be specified to be provided by the Contractor as a submittal item to be reviewed by the <br />Engineer. <br />17. Base Proposal assumes all electrical equipment is housed in suitable outdoor rated enclosures. <br />Task 4.1 – Prepare 60% Plans, Specifications and Cost Estimate: <br />The consultant team will develop 60-percent design documents building on the work of the Basis of Design Report. <br />Drawings, key specifications, and a preliminary Opinion of Probable Cost of Construction will be included by the <br />consultant team at the 60-percent level of design. A list of all planned project drawings and specifications will also <br />be provided with the 60% design submittal. <br />The 60-percent drawings will include the following: <br />Title Sheet & Sheet Index <br />Standard Notes, Abbreviations, and Details <br />Civil Plans, including Survey Control, Demolition, and Site Plans for the Pump Station and Pond Modifications <br />Mechanical Equipment Plans, Sections and Details <br />Wetwell, Pump & Piping Plans and Sections Including Operating Level Setpoint Information <br />Trash rack Equipment Plan and Section <br />Structural Plans <br />Pump Station Wetwell Structure <br />Electrical Building Floor and Roof Plans (optional) <br />Electrical and Instrumentation Plans <br />Motor Control Center & Switchgear Elevations <br />Single Line Diagram <br />Load Calculations <br />Site Plan <br />Building Electrical Plan (optional) <br />Pump Station P&ID <br />Impressed Current Cathodic Protection System (optional) <br />ATTY/AGR.2021.257/Wood Rodgers, Inc. (Bradford Storm Drain Pump Station Design) (Page 23 of 40)