Laserfiche WebLink
ID Task Name Duration Start Finish Predecessors <br />1 NTP 1 day Mon 1/3/22 Mon 1/3/22 <br />2 TASK 1 - PROJECT MANAGEMENT 269 days Tue 1/11/22 Fri 1/20/23 <br />3 Kick-off Meeting 1 day Tue 1/11/22 Tue 1/11/22 1FS+1 wk <br />4 QA/QC, Invoicing, and Progress Meetings 268 days Wed 1/12/22 Fri 1/20/23 3 <br />5 TASK 2 - SURVEYING & UTILITY RESEARCH <br />INVESTIGATIONS <br />12 days Wed 1/12/22 Thu 1/27/22 <br />6 Utility Research 3 days Wed 1/12/22 Fri 1/14/22 3 <br />7 Field Reconnaisance 1 day Thu 1/20/22 Thu 1/20/22 6FS+3 days <br />8 Topographic & Utility Field Survey 1 wk Fri 1/21/22 Thu 1/27/22 7 <br />9 TASK 3 - BASIS OF DESIGN 25 days Mon 1/17/22 Fri 2/18/22 <br />10 Basis-of-Design 25 days Mon 1/17/22 Fri 2/18/22 <br />11 Design Review Meeting 1 day Fri 1/28/22 Fri 1/28/22 8 <br />12 Establish Design Criteria 4 days Mon 1/31/22 Thu 2/3/22 11 <br />13 Hydraulic Modeling & Pump Design 1 wk Fri 2/4/22 Thu 2/10/22 12 <br />14 PG&E Coordination 1 wk Mon 1/17/22 Fri 1/21/22 6 <br />15 Schematic Electrical Design 2 wks Mon 1/17/22 Fri 1/28/22 14SS <br />16 BOD Submittal 1 wk Mon 1/31/22 Fri 2/4/22 15 <br />17 City Review 2 wks Mon 2/7/22 Fri 2/18/22 16 <br />18 TASK 4 - 60% Design Submittal 31 days Mon 2/21/22 Mon 4/4/22 <br />19 Design Review Meeting 1 day Mon 2/21/22 Mon 2/21/22 17 <br />20 60% Plans, Specifications, and Estimate 3 wks Tue 2/22/22 Mon 3/14/22 19 <br />21 60% Submittal 1 wk Tue 3/15/22 Mon 3/21/22 20 <br />22 City Review 2 wks Tue 3/22/22 Mon 4/4/22 21 <br />23 TASK 5 - 90% DESIGN SUBMITTAL 26 days Tue 4/5/22 Tue 5/10/22 <br />24 Design Review Meeting 1 day Tue 4/5/22 Tue 4/5/22 22 <br />25 90% Plans, Specifications, and Estimate 2 wks Wed 4/6/22 Tue 4/19/22 24 <br />26 90% Submittal 1 wk Wed 4/20/22 Tue 4/26/22 25 <br />27 City Review 2 wks Wed 4/27/22 Tue 5/10/22 26 <br />28 TASK 6 - FINAL SUBMITTAL (100% DESIGN <br />SUBMITTAL) <br />14 days Wed 5/11/22 Mon 5/30/22 <br />29 Design Review Meeting 1 day Wed 5/11/22 Wed 5/11/22 27 <br />30 100% Plans, Specifications, and Estimate 2 wks Thu 5/12/22 Wed 5/25/22 29 <br />31 Final Submittal 3 days Thu 5/26/22 Mon 5/30/22 30 <br />32 TASK 7 - BID SUPPORT & CONSTRUCTION <br />SERVICES <br />160 days Tue 6/14/22 Mon 1/23/23 <br />33 Bidding Phase Assistance 6 wks Tue 6/14/22 Mon 7/25/22 31FS+2 wks <br />34 Construction Phase Assistance 4 mons Tue 10/4/22 Mon 1/23/23 33FS+10 wks <br />35 TASK 8 - PUMP STATION No. 9 PROJECT 270 days Tue 1/11/22 Mon 1/23/23 <br />36 Task 1 through Task 7 270 days Tue 1/11/22 Mon 1/23/23 3SS <br />1/3 1/3 <br />1/11 1/11 <br />1/12 1/20 <br />1/12 1/14 <br />1/20 1/20 <br />1/21 1/27 <br />1/28 1/28 <br />1/31 2/3 <br />2/4 2/10 <br />1/17 1/21 <br />1/17 1/28 <br />1/31 2/4 <br />2/7 2/18 <br />2/21 2/21 <br />2/22 3/14 <br />3/15 3/21 <br />3/22 4/4 <br />4/5 4/5 <br />4/6 4/19 <br />4/20 4/26 <br />4/27 5/10 <br />5/11 5/11 <br />5/12 5/25 <br />5/26 5/30 <br />6/14 7/25 <br />10/4 1/23 <br />1/11 1/23 <br />S T M F T S W S T M F T S W S T M F T S W S T M F T <br />Dec 12, '21 Jan 23, '22 Mar 6, '22 Apr 17, '22 May 29, '22 Jul 10, '22 Aug 21, '22 Oct 2, '22 Nov 13, '22 Dec 25, '22 Feb 5, '23 Mar 19, '23 <br />Task <br />Split <br />Milestone <br />Summary <br />Project Summary <br />Inactive Task <br />Inactive Milestone <br />Inactive Summary <br />Manual Task <br />Duration-only <br />Manual Summary Rollup <br />Manual Summary <br />Start-only <br />Finish-only <br />External Tasks <br />External Milestone <br />Deadline <br />Critical <br />Critical Split <br />Progress <br />Manual Progress <br />Page 1 <br />Project: RWC PS No.8 <br />Date: Tue 12/21/21 <br />EXHIBIT B <br />REV: 12-22-21 JB <br />ATTY/AGR.2021.331/BKF Engineers (Sanitary Sewer Pump Station No. 8 and No. 9 Design) (Page 21 of 23)