ID Task Name Duration Start Finish Predecessors <br />1 1 PROJECT START-UP / KICKOFF 58 days Wed 8/30/23 Mon 11/20/23 <br />2 1.1 Selection Notification 0 days Wed 8/30/23 Wed 8/30/23 <br />3 1.2 Contract Negotiation 43 days Wed 8/30/23 Fri 10/27/23 <br />4 1.3 Board of Supervisor Meeting 0 days Mon 11/13/23 Mon 11/13/23 <br />5 1.4 Notice to Proceed Issued / Contract Executed 0 days Mon 11/20/23 Mon 11/20/23 4FS+1 wk <br />6 2 SITE SURVEYS AND INVESTIGATIONS 60 days Mon 11/20/23 Fri 2/9/24 <br />7 2.1 Utility Research & Site Investigations 2 wks Mon 11/20/23 Fri 12/1/23 5 <br />8 2.2 Topographic Field Survey 4 wks Mon 11/20/23 Fri 12/15/23 5 <br />9 2.3 Structural Assessment 4 wks Mon 11/20/23 Fri 12/15/23 5 <br />10 2.4 Geotechnical Investigation 8 wks Mon 12/18/23 Fri 2/9/24 9 <br />11 3 HYDROLOGIC AND HYDRAULIC ANALYSIS & PHYSICAL MODELING 185 days Mon 12/25/23 Fri 9/6/24 <br />12 3.1 H&H Analysis 3 wks Mon 12/25/23 Fri 1/12/24 21 <br />13 3.2 System Recommendations 3 wks Mon 1/15/24 Fri 2/2/24 12 <br />14 3.3 Physical Modeling 60 days Mon 6/17/24 Fri 9/6/24 <br />15 3.3.1 Initial Modeling & Report Development 8 wks Mon 6/17/24 Fri 8/9/24 36 <br />16 3.3.2 Draft Physical Modeling Report 0 days Fri 8/9/24 Fri 8/9/24 15 <br />17 3.3.3 City Review Period 2 wks Mon 8/12/24 Fri 8/23/24 16 <br />18 3.3.4 Physical Modeling Revisions 2 wks Mon 8/26/24 Fri 9/6/24 17 <br />19 3.3.5 Physical Modeling Report 0 wks Fri 9/6/24 Fri 9/6/24 18 <br />20 4 ALTERNATIVES ANALYSIS AND BASIS OF DESIGN REPORT 55 days Mon 12/18/23 Fri 3/1/24 <br />21 4.1 Preliminary Pump Design 1 wk Mon 12/18/23 Fri 12/22/23 9 <br />22 4.2 Preliminary Layouts & Vehicle Access 2 wks Mon 12/25/23 Fri 1/5/24 21 <br />23 4.3 Surge & Noise Analyses 1 wk Mon 1/8/24 Fri 1/12/24 22 <br />24 4.4 Draft BOD Report 3 wks Mon 1/8/24 Fri 1/26/24 22 <br />25 4.5 City Review Period 3 wks Mon 1/29/24 Fri 2/16/24 24,23 <br />26 4.6 Draft BOD Comment Coordination 1 wk Mon 2/19/24 Fri 2/23/24 25 <br />27 4.7 Revised BOD Report 1 wk Mon 2/26/24 Fri 3/1/24 26 <br />28 5 ENVIRONMENTAL AND PERMITTING 10 days Mon 6/17/24 Fri 6/28/24 <br />29 5.1 Permit Technical Memorandum 2 wks Mon 6/17/24 Fri 6/28/24 36 <br />30 6 60% INITIAL DESIGN SUBMITTAL 80 days Mon 2/26/24 Fri 6/14/24 <br />31 6.1 60% Construction Documents & Technical Studies 10 wks Mon 2/26/24 Fri 5/3/24 8,10,26 <br />32 6.2 60% Initial Design Submittal 0 days Fri 5/3/24 Fri 5/3/24 31 <br />33 6.3 City Review Period 4 wks Mon 5/6/24 Fri 5/31/24 32 <br />34 6.4 60% Comment Coordination 1 wk Mon 6/3/24 Fri 6/7/24 33 <br />35 6.5 60% Plan Revisions 1 wk Mon 6/10/24 Fri 6/14/24 34 <br />36 6.6 Revised 60% Initial Design Submittal 0 days Fri 6/14/24 Fri 6/14/24 35 <br />37 7 90% SEMI-FINAL DESIGN SUBMITTAL 55 days Mon 8/5/24 Fri 10/18/24 <br />38 7.1 90% Construction Documents & Technical Studies 6 wks Mon 8/5/24 Fri 9/13/24 36,14FF+1 wk <br />39 7.2 90% Semi-Final Design Submittal 0 days Fri 9/13/24 Fri 9/13/24 38 <br />40 7.3 City Review Period 4 wks Mon 9/16/24 Fri 10/11/24 39 <br />41 7.4 90% Comment Coordination 1 wk Mon 10/14/24 Fri 10/18/24 40 <br />42 8 FEMA REVIEW 120 days Mon 9/16/24 Fri 2/28/25 <br />43 8.1 Grant Administrator / FEMA Review 6 mons Mon 9/16/24 Fri 2/28/25 39 <br />44 9 100% FINAL DESIGN SUBMITTAL 43 days Mon 3/3/25 Wed 4/30/25 <br />45 9.1 100% Construction Documents & Technical Studies 4 wks Mon 3/3/25 Fri 3/28/25 41,43 <br />46 9.2 100% Final Design Submittal 0 days Fri 3/28/25 Fri 3/28/25 45 <br />47 9.3 City Review Period 4 wks Mon 3/31/25 Fri 4/25/25 46 <br />48 9.4 Stamped and Signed Construction Documents 0 days Wed 4/30/25 Wed 4/30/25 47FS+3 days <br />49 10 BID SUPPORT & CONSTRUCTION SERVICES 320 days Thu 5/1/25 Wed 7/22/26 <br />50 10.1 Bidding Phase 2 mons Thu 5/1/25 Wed 6/25/25 48 <br />51 10.2 Construction Phase 12 mons Thu 6/26/25 Wed 5/27/26 50 <br />52 10.3 Construction Complete 0 days Wed 5/27/26 Wed 5/27/26 51 <br />53 10.4 Project Close-out and Record Drawings 2 mons Thu 5/28/26 Wed 7/22/26 52 <br />8/30 <br />11/13 <br />11/20 <br />11/20 12/1 <br />11/20 12/15 <br />11/20 12/15 <br />12/18 2/9 <br />12/25 1/12 <br />1/15 2/2 <br />6/17 8/9 <br />8/9 <br />8/12 8/23 <br />8/26 9/6 <br />9/6 <br />12/18 12/22 <br />12/25 1/5 <br />1/8 1/12 <br />1/8 1/26 <br />1/29 2/16 <br />2/19 2/23 <br />2/26 3/1 <br />6/17 6/28 <br />2/26 5/3 <br />5/3 <br />5/6 5/31 <br />6/3 6/7 <br />6/10 6/14 <br />6/14 <br />8/5 9/13 <br />9/13 <br />9/16 10/11 <br />10/14 10/18 <br />9/16 2/28 <br />3/3 3/28 <br />3/28 <br />3/31 4/25 <br />4/30 <br />5/1 6/25 <br />6/26 5/27 <br />5/27 <br />5/28 7/22 <br />Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug <br />2024 2025 2026 <br />Task <br />Split <br />Milestone <br />Summary <br />Project Summary <br />Inactive Task <br />Inactive Milestone <br />Inactive Summary <br />Manual Task <br />Duration-only <br />Manual Summary Rollup <br />Manual Summary <br />Start-only <br />Finish-only <br />External Tasks <br />External Milestone <br />Deadline <br />Critical <br />Critical Split <br />Progress <br />Manual Progress <br />Page 1 <br />Project: Price Tract SD PS <br />Date: Mon 10/23/23 <br />REV: 11-07-23 SK <br />ATTY/AGR.2023.241/BKF Engineers (Price Tract Pump Station Design) (Page 58 of 68)