ATTY/RESO.0034/CC RESO APPROVING PROJECT (901 EL CAMINO REAL) – EXHIBIT A <br />REV: 04-22-25 VR <br />Page 14 of 28 <br />• Treatment Measure Inspection – The Applicant shall coordinate installation of <br />stormwater treatment measures with the municipality, shall arrange to have the <br />City’s designated inspector present at the time of installation, and shall have the <br />City’s designated inspector complete a final inspection of installed stormwater <br />treatment measure immediately after installation is complete. <br />54. Stormwater Management Plan (SWMP) – The Applicant shall prepare a SWMP that <br />includes, at a minimum, exhibit(s) showing drainage areas and location of Low Impact <br />Development (LID) treatment measures; total project site area and total area of land <br />disturbed; total new and/or replaced impervious area; treatment measures and hydraulic <br />sizing calculations; a listing of source control and site design measures to be implemented <br />at the site; saturated hydraulic conductivity rate(s) at relevant locations or hydrologic soil <br />type (A, B, C or D) and source of information; elevation of high seasonal groundwater table; <br />and a brief summary of how the Project is complying with Provision C.3 of the MRP. <br />[COA][ENGINEERING] <br />55. Construction General Permit – For construction activity resulting in a land disturbance of <br />one acre or more, the Applicant shall file a Notice of Intent (NOI) with the State Water <br />Resources Control Board under the Construction Activities Storm Water General Permit <br />(General Permit). The NOI indicates the Applicant’s intent to comply with the San Mateo <br />Countywide Stormwater Pollution Prevention Program, including a Stormwater Pollution <br />Prevention Plan (SWPPP). [SDR] [ENGINEERING] <br />56. Stormwater BMPs - Stormwater Pollution Prevention Program Best Management Practices <br />(BMPs) for construction shall be implemented by the Applicant to protect water quality, in <br />accordance with the approved Stormwater Pollution Prevention Plan (SWPPP). BMP plan <br />sheets are available electronically for inserting into project plans. [SDR][ENGINEERING] <br />Street Infrastructure Improvements <br /> <br />57. Streetlights - The Applicant shall install a new streetlight, if needed, as determined by the <br />City Engineer. Streetlights are required on the construction of a new commercial building <br />or performance of substantial commercial remodeling with street frontage of 200 feet or <br />more. The style and location of all streetlights shall be as determined by the City Engineer <br />and Planning Manager. [SDR][ENGINEERING] <br /> <br />58. Green Infrastructure Improvements – The Applicant shall include stormwater treatment <br />systems, including but not limited to Silva Cells, at the project frontages along James <br />Avenue, Winklebleck Street, new Franklin Street and El Camino Real. The treatment <br />systems shall be sized to treat the half-street tributary area of the project frontage. <br />[SDR][ENGINEERING] <br />59. Repair or Replace Street Infrastructure – The Applicant shall restore streets and street <br />infrastructure surrounding the project site to the satisfaction of the City Engineer at project <br />completion. At the minimum, this shall mean grind and overlay of half width of the frontage