Redwood City Stormwater Roadmap
<br />Recommended Assessments
<br />September 2025 6-7 Schaaf & Wheeler
<br />Table 6-1: Stormwater Master Plan Cost Estimate
<br />Stormwater Master Plan Elements Cost Estimate Range
<br />Data Gaps Analysis $10,000 to $20,000
<br />Topographic Surface Information Collection $300,000 to $600,000
<br />Infrastructure Data Collection and Condition
<br />Assessment
<br /> Pipes $200,000 to $400,000
<br /> Concrete and Natural Channels $150,000 to $300,000
<br /> Culverts and Bridges $40,000 to $60,000
<br /> Basins and Lagoons $60,000 to $90,000
<br /> Pump Stations $60,000 to $80,000
<br /> Green Infrastructure $30,000 to $50,000
<br />Hydrologic and Hydraulic Modeling $200,000 to $400,000
<br />Climate Change Projections $40,000 to $60,000
<br />Shoreline Infrastructure $20,000 to $40,000
<br />Identifying and Prioritizing Capital Improvement
<br />Projects $60,000 to $80,000
<br />Cost Estimate $10,000 to $20,000
<br />Public Outreach $30,000 to $50,000
<br />Funding Feasibility Study $50,000 to $100,000
<br />O&M Assessment $40,000 to $60,000
<br />Developing the Master Plan $40,000 to $50,000
<br />Conceptual Designs $50,000 to $100,000
<br />Total Individual Costs $1,400,000 to $2,600,000
<br />Total Costs if Completed Together $1,100,000 to $2,100,000
<br />Total Savings $300,000 to $500,000
<br />
<br />6.2 Regulatory Compliance Projects
<br />In addition to the Stormwater Master Plan, the City should be adhering towards near-term and
<br />ongoing compliance projects, like the National Pollutant Discharge Elimination System (NPDES)
<br />and the Regional Shoreline Adaptation Plan (RSAP). While both are inherently separate efforts
<br />to the Stormwater Master Plan, they may complement each other, which would streamline
<br />processes for the City.
<br />6.2.1 NPDES Compliance
<br />Redwood City, as a regulated Phase I MS4 permittee, must comply with the NPDES MRP 3.0,
<br />issued by the San Francisco Bay Regional Water Quality Control Board and effective July 1, 2022.
<br />The City is required to reduce pollutants in stormwater runoff through provisions related to new
<br />development (Provision C.3), trash load reduction (Provision C.10), illicit discharge control, and
<br />public education.
<br />Under Provision C.10, Redwood City must achieve full compliance with trash capture
<br />requirements, either through full trash capture systems or equivalent measures, by December 31,