6.1 E <br /> Bid Reject Page 2 <br /> The apparent low bid of $1,261,f84.65 submitted by Elite Landscaping Inc. is 26°/a <br /> lower than#he enginees's estimate of$'1,698,033.00 for fhe cost of constructian, and the <br /> apparent second low bid of $1,330,89�.00 submitted by Goodland Landscape <br /> Construction Inc. is 22% lower than the engineer's estimate. However, s#aff has <br /> determinet#the law bid to be"not responsible"due to lack of experience on projects of a <br /> simiiar nature, and the second low bid to be"non-responsive." The Addendum No.1 to <br /> the Contract Documents, states "minimum experrence requiremenfs of the prrme <br /> contractor shal! rnclude the complefion of 5 projects, each of whrch included the <br /> insta!lation of synthefic turf playing frelds af least 50,000 s.f in size, involving contract <br /> d�llar amounts of ar least$�million each, within fhe past 5 years." Staff has evaluated <br /> the experiences of Elite Landscaping (nc. and Goodland Landscape Consfirucfiion, Inc., <br /> and contacted the references�rovided. <br /> Elite Landscaping [nc. has been determined "not responsibfe° because of the seven <br /> proyects provided as reference, four projects are located outside of the United States, <br /> one project was not completed within the past fi�e years, one project contact number is <br /> disconnected, and one project contact stated that fhe projec# cor�tractor was not Elite <br /> Landscaping 1nc. Eiite claims that the project for which the project contact states Elite <br /> was not the contractor should be attributable to Elite because current Elite project <br /> manager, Sergio Del Rio, worked on that project, even though at the time Mr. Rio was <br /> working for a different contract company; the City has determined that the project <br /> cannot be attrib�table ta El�te. <br /> On March 5, 201 a Elite Landscaping Inc. submitted an electranic message con#aining <br /> addifionaE foreign project references. Staff responded by s#ating "due to differences in <br /> standards, such as testing, compliance, and publi� contract code, projects performed <br /> outside of the Unites States can not be considered as similar,comparable projects",and <br /> requested domestic pro�ect references from Elite. In addition, on March 16, 2010, staff <br /> requested that Elite submit copies of the contract dacuments for the foreign projects <br /> referenced tha#show Elite as the general contractor. As of the end of business March <br /> 17, 2010, staff has not received any of the requested documents from Eli#e. Based on <br /> the foregoing facts, City Staff a�rms its initial determination that Elite Landscaping, Inc. <br /> is not responsible. <br /> Goodland Landscape Constructian, Inc. has beer� determined "non-responsive" <br /> because two of the five synthetic field prajects submitted were not completed within the <br /> past five years as documented by#he Notice of Completion filed by the owner. <br /> Bid Award <br /> The third lowest bidder, Robert A. Bothman, Inc., submitted a responsive and <br /> responsible bid of $1,421,128.00, which is 16% lower than the engineer's estimate. <br /> Robert A. Bothman, Inc. has successfully completed similar projects in the past and is a <br /> quali�ed contractor. Based o� the bids received, staff recammends award of the <br /> contract to Robert A. Bo#hman, Inc. <br /> ALTERNATIVE5 <br /> Council may choose nofi to award the contract and direct staff to rebid this project. <br /> FISCAL IMPACT <br /> Funds far the turf conversion work of this project have been previously appropriated as <br /> Water Bond Projects Fund — Recycled Wafer System Development which has an <br /> available balance of $894,135.00 for the turf replacement prograrn. Funds for <br />