would remain. The adjacent dirt area just north of the ramp or the bare area between the railroad tracks <br /> would be used for materials and equipment staging,and construction vehicle parking. <br /> Construction Scheduling; <br /> The demolition of existing structures and replacement of new structures is anticipated to occur over a <br /> three-month period. Pile driving is anticipated to take a maximum of 2 to 3 days to extract the 8 existing <br /> concrete piles and to drive the 2 replacement piles. Crane operations to demolish the pier and install the <br /> gangway are expected to occur over another 2 to 3 day period.The remainder of the construction <br /> activities involving concrete forming and dock assembly would be accomplished using hand or small <br /> power tools. <br /> Port of Redwood City Multi-Agency Maritime Facility 6 February 2010 <br /> Initial Study <br />