description may require changes to this scope and budget. It is assumed the technical documents
<br /> provided by the applicant are adequate to document changes to the environment of the project and
<br /> adequately describe the existing conditions.
<br /> The ADEIR will include a summary, introduction, project description, environmental analysis, CEQA
<br /> mandated discussions, and potential mitigation measures. Each environmental analysis section will
<br /> include a setting, thresholds, methodology, and environmental analysis. The alternatives analyzed in the
<br /> ADEIR, at a minimum, will include No Project and Full Site Restoration. Up to two additional
<br /> alternatives may be evaluated that avoid or reduce environmental impacts based on the environmental
<br /> analysis. An Alternatives workshop will be conducted.
<br /> The ADEIR will be provided to the City and ERMT for review and feedback. The ECT shall revise the
<br /> ADEIR as directed by the City.
<br /> Schedule
<br /> Amendment No. 3 extends the Amended Scope of Work through June 2012.
<br /> Estimated Budget
<br /> The estimated budget includes . ... • , - . - . . , ., - . • - - .. , • , • • - - - • - - e ' - - , ••. , • , "' $995,000 of funds allocated by this
<br /> Amendment No. 2-3.
<br /> Task Labor Direct Costs* Total
<br /> 1 Program Management/Coordination $ 1 98,900 $284,1 $443,070
<br /> $320,900 $326,200 $647,100
<br /> 2 Project and Administrative Record SI8,600 $3.7,,,00
<br /> $22,600 $18,900 $41,500
<br /> 3 Identification of Agencies and Experts $21,100 $54,400 $75,500
<br /> 4 Environmental Table of Contents and $54,700 $209,400 $264,100
<br /> Sections
<br /> 5 Scoping Preparation
<br /> $39,000 $65,000 $104,000
<br /> 6 Project Scoping #1 $385,100 $767,030 $1,152,130
<br /> $705,000 $1,090,100
<br /> 7 Project Scoping #2 $44,900 $30,100 $75,000
<br /> 8 Preparation of Draft Environmental $105,700 $708,300 $814,000
<br /> Documents
<br /> Total $747,400 $4498900 $2,- 1 16. 300
<br /> $994,000 $2,117,300 $3,111,300
<br /> *Includes subcontractors
<br /> Saltworks Environmental Program Task Order No. 004 Page 12