Laserfiche WebLink
<br />Bill of Materials, page 4 of 4 <br /> <br />V. Comment: <br /> <br />The above quoted pumps and motors are of duplicate construction to the previously furnished <br />equipment currently installed in the Redwood City Recycled Water Project Phase 1,2005-06. <br />The pumps will be furnished to install in the existing Suction Cans, without any modification. <br /> <br />2.03.CA.b.1), All field machining of the pump's cans is specifically excluded from this scope of <br />supply and is by the installing contractor. <br /> <br />2.03.CA.c., Flowserve can accommodate special drilling on the discharge heads, the contractor <br />will need to field verify each of the respective pump's installation. <br /> <br />2.03.D.3, Flowserve has confirmed on the previous order that the 12 inch discharge head will <br />match a 90.90 elevation for the bottom of discharge mounting flange and a 91.90 centerline <br />of discharge, contractor will need to field verify. <br />