Laserfiche WebLink
TIME SCHEDULE: <br /> The timeline for preparation and completion of the IS/MND is as follows: <br /> Task or Deliverable Weeks to Complete Total Weeks from <br /> Signed Contract <br /> Receive Authorization to One week 1 <br /> Proceed/Initiate Task 1; <br /> Cornerstone to begin Geotechnical <br /> Investigation <br /> Cornerstone Complete Approximately 5 weeks from start of 6 <br /> Geotechnicallnvestigation project <br /> Delivery of Admin. Draft IS/MND Approximately 4 weeks from receipt 10 <br /> and Mitigation Monitoring and of all substantial project information <br /> Reporting Program (MMRP) including geotechnical investigation <br /> City of Redwood City Review Approximately three weeks from 13 <br /> delivery of Admin. Draft IS/MND <br /> Delivery and release of Public Draft Approximately two weeks after 15 <br /> IS/MND and Notice of Intent to receipt of comments on the <br /> Adopt Negative Declaration administrative draft* <br /> Public Review 30 days 19 <br /> Public Hearing(s) (optional, not Within the 30-day public review -- <br /> required) period <br /> Review of public comments; Approximately three weeks after 22 <br /> Preparation of Response to receipt of all comments <br /> Comments(RTC) memo <br /> Adoption of IS/MND and MMRP; Approximately two weeks after 24 <br /> Project Approval receipt response to comments <br /> memo;to be held at a regularly <br /> scheduled City Council meeting <br /> Notice of Determination Filed Must be filed within five working days 25 <br /> after approval of the project <br /> ATTY/AGR/2012.073lfRA ENVIRONMENTAL SCIENCES,INC <br /> REV:06-05-12 VR Page 23 of 26 <br />