Laserfiche WebLink
TIME SCHEDULE <br /> The project schedule is as follow: <br /> 1. Notice to Proceed (NTP)—Provided by the City <br /> 2. 75% Design Submittal—2 weeks after NTP <br /> 3. City Review and Comments—2 weeks after 75% Design Submittal <br /> 4. 100% Construction Documents— 1 week after receipt of City Comments <br /> 5. Project out to Bid— Determined by City <br /> 6. Construction Phase—Determined by City <br /> FEE SCHEDULE <br /> Task 1�ours Total <br /> WES ASST CAD <br /> 1 Project�tart-up, Existing Document Retrieval & Review 1 $15p <br /> 2 Site Investigations/�urveys 2 $300 <br /> 3 Prepare Dra�.vings 3 $450 <br /> Prepare Specs(Including Coordination with City's Front <br /> 4 End Specs) 3 $450 <br /> 5 Preparation of Opinion of Probable Cost 1 $150 <br /> 6 Package Documents for Bid 1 $150 <br /> Total 11 $1,650 <br /> 7 Construction Admin. (blled as actual hours consumed}not to exceed: $150 <br /> 8 Design Meetings{billed as actual hours consumedj not to exceed: $150 <br /> Total : 1,950 <br /> Rate Schedule <br /> Wes Stout $150/hour <br /> Assistant $120/hour <br /> CAD Modeler/Drafter $100/hour <br /> City Attorney Approved Version#05.22.01 <br /> 6 <br />