Laserfiche WebLink
SECTION 01200 <br /> MEASUREMENT& PAYMENT <br /> 1.0 GENERAL <br /> A. The total Bid price shall cover all work necessary for the proper and successful completion of the <br /> Contract. All work not specifically set forth as a pay item in the Bidder's Bid, but necessary to meet the <br /> requirements of this Contract, shall be considered a subsidiary obligation of the Contractor, and all <br /> costs in connection therewith shall be included in the prices Bid. <br /> B. All estimated quantities stipulated in the Bid form are to be used only as a basis for estimating the <br /> probable cost of the work and/or for the purpose of comparing the Bids submitted for the work. The <br /> actual amounts of work completed under unit price items may differ from estimated quantities. The <br /> basis of payment for unit price work will be the actual amount of work completed. Contractor agrees to <br /> make no claim for damages anticipated profits or otherwise on account of any difference in the amounts <br /> of work actually performed, and estimated amounts therefore. <br /> 1.01 MOBILIZATION, DEMOBILIZATION AND OTHER INCIDENTALS (BID ITEM N0. 1) <br /> A. Full compensation for all mobilization consisting of preparatory work and operations, including, but not <br /> limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the <br /> project site, traffic control measures including supplying, maintaining all traffic signs, portable <br /> barricades and delineators required, any required flagging costs, as necessary to implement traffic <br /> control measures will be considered as included in the lump sum price paid for MOBILIZATION, <br /> DEMOBILIZATION AND OTHER INCIDENTALS and no separate payment will be made therefore. <br /> Attention is directed to Sections 7-1.03, "Public Convenience," 7-1.04, "Public Safety," 12-3.04, <br /> "Portable Delineators," and 12-1.03 "Flagging Costs," of the Standard Specifications and these Special <br /> Conditions. The Contractor shall cooperate with local authorities relative to handling traffic through the <br /> area, and shall make his own arrangements relative to keeping the work area clear of parked vehicles. <br /> B. Full compensation for restoring existing landscape and damaged structures, and other incidentals <br /> related to the completion of this Project shall be included as a lump sum price paid for MOBILIZATION, <br /> DEMOBILIZATION AND OTHER INCIDENTALS. This work shall include, but is not limited to: <br /> verification and location of existing equipment, restoration of damaged equipment, furnishings finishes <br /> and structures due to installation of the improvements shall be to restored or replaced in kind to the <br /> satisfaction of the City. <br /> 1.02 RENOVATE INTERIOR ELEVATOR CAB (BID ITEM NO. 2) <br /> A. The contract unit price paid for each interior elevator cab renovation shall include full compensation for <br /> furnishing all labor, materials, tools, equipment, and incidentals for performing all the work required to <br /> refinish all visible interior surtaces of each cab. Work includes, but is not limited to transporting the <br /> equipment to the project site; removal and disposal of existing finishes and any associated substrate; <br /> dust control; clean up; re-facing of existing cab walls, doors, door returns and soffits; furnishing and <br /> installing new steel faced cab panels; furnishing and installing new handrails; furnishing and installing <br /> new cab ceiling and lights; temporary disconnection of controls and power, reconnection of electrical <br /> control board; making all electrical connections; and any other miscellaneous work items necessary to <br /> provide a complete, functioning system. Elevator cab panels, handrails, cab ceiling, cab door and lights <br /> shall be installed in accordance with manufacturer's specifications and recommendations. <br /> B. Full compensation for all additional materials and labor, not shown on the plans or specified, which are <br /> necessary to complete the installation of the various systems, shall be considered as included in the <br /> contract unit price paid for the installation, or units thereof, and no additional compensation will be <br /> allowed therefore. <br /> C. Individual parts and components will not be measured for payment, but shall be included in the unit <br /> price paid for each"Renovate Interior Elevator Cab." <br /> MEASUREMENT&PAYMENT <br /> MARSHALL STREET GARAGE ELEVATOR <br /> REFURBISHMENT PROJECT 01200-1 <br />