<br /> Task JME MID DLH Drafting FUGRO ODCs Labor Total
<br /> $224 $198 $177 $125 $200
<br /> Task la Steel Tanks and Pipes
<br /> Inspection and Site Visit 8 10 10 $100 $5,542 $5,642
<br /> Pipes Develop 25%&50%Design,Submit 8 28 32 32 $17,000 $17,000
<br /> Anchors Develop 25.50%Design,Submit 12 28 40 36 16 $400 $23,012 $23,412
<br /> Specs,Develop Submit 90s 8 16 24 24 $400 $12,208 $12,608
<br /> Submit 100 for Bid g 8 8 8 $400 $5,792 $6,192
<br /> Subtotal Task 1a 44 90 114 100 16 $1,300 $63,554 $64,854
<br /> Task lb Redwood Shores Pipe Bridges
<br /> Inspection, Data Collect and Site Visit 8 8 $100 $3,376 $3,476
<br /> Evaluate Bridge/Pipes 16 8 24 8 $11,016 $11,016
<br /> Report and Progress meeting 8 4 2 $2,984 $2,984
<br /> Develop 25%&50%Design,Submit 8 16 16 20 $200 $10,292 $10,492
<br /> Specs,Develop Submit 90s 4 8 8 12 $200 $5,396 $5,596
<br /> Submit 100 for Bid 2 2 4 8 $200 $2,552 $2,752
<br /> Subtotal Task lb 46 46 52 40 10 $700 $35,616 $36,316
<br /> Task 2 Carson Reservoir
<br /> Interior inspection 8 8 $100 $3,208 $3,308
<br /> Develop 25%&50%Design,Submit 16 60 90 90 $400 $42,644 $43,044
<br /> Specs,Develop Submit 90s 16 40 50 50 $400 $26,604 $27,004
<br /> Submit 100 for Bid 8 20 40 20 $400 $15,332 $15,732
<br /> Subtotal Task 2 48 120 188 160 0 $1,300 $87,788 $89,088
<br /> Task 3 Equipment and Structures
<br /> Inspection and Site Visit 8 8 $3,000 $3,000
<br /> Develop 25%&50%Design,Submit 8 18 18 18 $300 $10,792 $11,092
<br /> Specs, Develop Submit 90s 4 8 8 16 $300 $5,896 $6,196
<br /> Submit 100 for Bid 2 4 4 8 $300 $2,948 $3,248
<br /> Subtotal Task 3 14 38 38 42 0 $900 $22,636 $23,536