Redwood Shores <br /> The electrical work at the Redwood Shores Parks continues to delay com- <br /> pletion of the project . This work is necessary for the completion and <br /> testing of the irrigation system as well as for the lighting of the <br /> tennis courts resulting in their completion . It is reported that the <br /> light poles and fixtures for the courts are scheduled to be received <br /> the second week of December . The electrical panel necessary for the <br /> lighting is delayed until the latter part of December . Other work has <br /> been completed such as the access walks in the park areas and the play <br /> apparatus areas except for the installation of the play equipment . <br /> This will be done as a part of the final completion of the project . <br /> -6 - <br />