My WebLink
|
Help
|
About
|
Sign Out
Browse
Search
PRC MIN 1976-05-12 and Special 5-20
RedwoodCity
>
Park and Rec Commission
>
Parks & Rec Comm Minutes
>
1970-1978
>
1976
>
PRC MIN 1976-05-12 and Special 5-20
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
12/4/2014 9:59:14 AM
Creation date
12/4/2014 9:53:59 AM
Metadata
Fields
Template:
Park and Rec Comm
Park and Rec Comm - Document Type
Minutes
Date
5/12/1976
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
16
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
PARKS & RECREATION DEPARTMENT MONTHLY REPORT <br /> DESIGN & DEVELOPMENT <br /> MAY 1976 <br /> Redwood Shores Park Development <br /> The construction drawings and specifications for Dolphin Parks I , II , <br /> and III and for the first phase of Marlin II Park are in the final <br /> stages of preparation . The staff together with the consultant , Recrea - <br /> tion Land Planners , met for a final review of the plans and specifica - <br /> tions May 27 . Various corrections and alterations resultant from this <br /> meeting are now being incorporated into the plans by the consultant . <br /> The Salt Water Intrusion Test Project being conducted by the Public Works <br /> Department was delayed approximately two weeks resultant from vandalism <br /> at the test site . The covers for the test wells were vandalized and the <br /> wells were filled with large rocks . The removal of these rocks was <br /> extremely difficult thus delaying the pumping of the test water from <br /> the wells from which the data is being accumulated regarding the salt <br /> water intrusion problem . New covers have now been secured on to the <br /> wells and pumping has resumed on a daily basis . It should be noted that <br /> the final drainage plans and specifications for the construction of the <br /> park areas must await the completion and the results of this test project . <br /> Any delay in the completion of the project will , of course , delay the <br /> completion of the plans and the calling for bids for the park construction . <br /> Every effort is being made to expedite these park projects as much as is <br /> practical . Barring further unforeseen circumstances the current schedules <br /> now indicate that bids can be called for the latter part of June or the <br /> first part of July . <br /> Belmont School District Site - - Redwood Shores <br /> The construction work for the grading , irrigation , and turfing of the area <br /> at the Belmont School District site in Redwood Shores is now approximately <br /> 80% complete . The irrigation has been installed , final grading of the area <br /> is now under way , and the sodding of the area is scheduled for the first <br /> part of June . The softball diamond has been laid out and the backstop is <br /> scheduled to be installed the first week of June . <br /> Palm Park <br /> Pre-construction meetings have been held with the Landscaping Division of <br /> the Davey Tree Surgery Company , the contractor for the first phase of <br /> construction of Palm Park . Current schedules call for work to be under <br /> -8 - <br />
The URL can be used to link to this page
Your browser does not support the video tag.