Exhibit "A" <br />SCOPE OF SERVICES AND FEE <br />The scope of services and compensation for Amendment No. 4 are described below. <br />Background <br />Caltrans requires formal traffic analysis of the five proposed stages of project <br />construction, which are defined in Stage Construction and Traffic Handling (SC/TH) plans. <br />This is necessary to provide Caltrans and the City with detailed data and findings about <br />traffic impacts that may arise during construction and determine whether potential <br />mitigations are feasible. <br />Consultant's Original Agreement Scope of Services (Task 2.6.11 Transportation <br />Management Plan) did not include the required traffic analysis because this activity was <br />not customary for Caltrans projects like the 101/84 (Woodside Road) Interchange <br />Improvement Project. Based on recent project experience with San Mateo County <br />interchange projects, Caltrans now requires additional information regarding this aspect <br />of project design. Staff concurs that this work is both necessary and is considered to be <br />additional work. <br />Scope of Work <br />Consultant will complete the scope of work described below as an extension of Task <br />2.6.11 Transportation Management Plan. <br />Purpose <br />• Determine whether SC/TH plans are functionally adequate for each stage as <br />compared to No Project conditions (in the year 2022) <br />• Determine if Lane Closure Charts are functionally adequate <br />• Identify and evaluate/assess possible layout changes <br />• Incorporate findings into 100% Design <br />Procedure <br />Consultant will use the existing Synchro/SimTraffic model and the existing AM and PM <br />peak hour traffic data that was used during the PA&ED phase of the work to evaluate <br />traffic operating conditions during each stage/phase of the project. <br />REV: 02-05-20 PR <br />ATN/AGR.Amend. No.4/AECOM (Page 3 of 7) <br />