<br />Lf.;2 B <br />(4) <br /> <br />Mr, Lowell Sue <br />City of Redwood City <br />October 4, 2000 <br />Page 2 <br /> <br />ITEM 3 NEW MEDIAN AT HASTING/SHORELINE (SHOPPING CENTER) <br /> <br />Item 3 is the extra work involved for the design and layout of a new median island on Hasting Shoreline Lane, This <br />work was originally noted in our contract addendum letter dated January 24, 1997 and attached letter. For this time, <br />we request a fee of $4,466,00 as itemized below: <br /> <br />Title <br />Principal <br />Sr. Project Manager <br />Engineer II <br />Engineer I <br /> <br />Hours <br />8.00 <br />10.00 <br />27.00 <br />3,00 <br /> <br />Rate <br />$135.00 <br />$113.00 <br />$ 76.00 <br />$ 68,00 <br />Subtotal <br /> <br />Total <br />$1,080,00 <br />$1.130,00 <br />$2,052.00 <br />$204.00 <br />$4,466.00 <br /> <br />ITEM 4 SHORELINE DRIVE RIGHT TURN LANE REVISION. (SHOPPING CENTER) <br /> <br />During design of the project the Shoreline Drive right turn lane was the subject of many changes due to ongoing <br />negotiations and design refinements occurring on the adjoining properties, This required us to redraft and layout the <br />turn lane through a number of iterations after the preliminary design was approved, We are requesting $4,129,00 <br />for this extra work item, <br /> <br />Title <br />Principal <br />Sr. Project Manager <br />Engineer II <br />Engineer I <br /> <br />Hours <br />6.00 <br />2,00 <br />29.50 <br />12.00 <br /> <br />Rate <br />$135,00 <br />$113,00 <br />$ 78.00 <br />$ 66,00 <br />Subtotal <br /> <br />Total <br />$810,00 <br />$226,00 <br />$2,301,00 <br />$792.00 <br />$4.129,00 <br /> <br />ITEM 5 RIGHT-OF-WAY ADJUSTMENTS BY CITY, <br /> <br />During the negotiations with the adjoining property owners and determination of the correct right-of-way layout, we <br />were far along in the development of our plans, Each time the right-of-way was changed or adjusted we were <br />required to make corresponding adjustment to our improvement plans to make them consistent with the right-of-way <br />dedications, Given that this right-of-way process became an iterative one. we made numerous repetitive changes to <br />our plan in order to keep them.in conformance with your right-of-way take proposals as outlined in our January 17, <br />1998 letter. We are requesting $3,324.00 for this work, This work was required because the City was modifying the <br />RO, W, and was in a negotiating process with the adjoining property owners, . <br /> <br />Title <br />Principal <br />Engineer II <br />Engineer I <br /> <br />Hours <br />4.00 <br />8,00 <br />32,00 <br /> <br />Rate <br />$135,00 <br />$ 76,00 <br />$ 68,00 <br />Subtotal <br /> <br />Total <br />$540.00 <br />$608,00 <br />$2,176,00 <br />$3.324,00 <br />