Furthermore, no additional easement will be provided for the contractor to do the work <br />beyond what was shown in the original bid documents. <br /> <br />The bid document stated that the contractors shall bid on a “base bid” as shown in the <br />project drawings and specifications plus “add alternate bid 1”, and plus “add alternate bid <br />2”, which together forms the “Total Bid.” The two add alternate bid schedules are each <br />distinctly separate segments of the creek when compared to the base bid segment of the <br />creek, but the two additional segments are near enough to the base bid segment that it <br />may be economical to do the additional work under one construction project. The low <br />bidder is determined by the Total Bid Amount. However, as shown in the project drawings <br />and specifications, the City retained the right to award a contract for the base bid only or to <br />award a contract with any combination of the base bid and add alternate bid 1 and 2 items. <br /> <br />The bid result with CO#1 amount is summarized in the tables below: <br /> <br /> <br />BIDDER BASE BID AMOUNT <br />Disney Construction Inc, $1,625,895.00 <br />Engineer’s Estimate $1,139,183.81 <br /> <br />BIDDER ADD ALTERNATIVE BID 1 AMOUNT <br />Disney Const. Inc. $137,880.00 <br />Engineer’s Estimate $184,880.64 <br /> <br />BIDDER ADD ALTERNATIVE BID 2 AMOUNT <br />Disney Const. Inc., (plus 60 LF of wall length and 30 <br />LF of concrete base slab) <br />$272,912.00 <br />Engineer’s Estimate $423, 591.17 <br /> <br />TOTAL BID AMOUNT (BASE BID + ADD ALTERNATE BID 1 + ADD ALTERNATE BID 2) - <br />JEFFERSON BRANCH <br />BIDDER TOTAL BID AMOUNT <br />(BASE BID + ADD ALTERNATE BID 1+ ADD <br />ALTERNATE BID 2 <br />Disney Const. Inc. $2,036,687.00 <br />ENGINEER’S ESTIMATE <br /> <br />$1,747,655.62 <br /> <br /> <br />Staff has evaluated the bids and has determined that the total price submitted by Disney <br />Construction Inc.is 16.53% higher than the engineer’s probable cost estimate for the cost <br />of construction. Staff believes the low number of bids received and high bid amount are <br />most likely attributed to the nature of this specialty project, a very competitive construction <br />market, permit requirements that limit capable contractors and the perception of risk <br />regarding working in a confined work site adjacent to multiple private properties. <br /> <br />6.1.E. - Page 3