6.R. - Page 3 of 10 <br />Below is a summary of the delays: <br />1. Electrical <br />a. Redesign and rerouting of underground electrical adjacent to sports field. <br />The 30 -acre community park has been built incrementally over many decades and throughout that time <br />some improvements have not been documented very well. During demolition, several utilities were <br />uncovered that were not recorded in the as-builts or were found in poor condition. Near the Griffin Field <br />sports field lights, a new pull box was required forthe electrical connection. This pullbox replaced a smaller <br />existing box that was in degraded. The new, safer box allows for ease of access and maintenance of the <br />lighting but added to the project time. This work also triggered revisions to the electrical plans to <br />accommodate the new electrical lines crossing the area dedicated to the new play areas. <br />b. City directed conduit and pull box additions at playhouse during installation. <br />For public safety inside the two-story play structure and the approach to the structure, additional pull <br />boxes and conduits were added to the playhouse to allow for future security cameras and exterior motion <br />sensor floodlights on the upper level for more lighting inside and outside of the playhouse. In addition, <br />the layout was changed for the security cameras in order to cover the elevated tree pod (retreat hut) <br />whose design was modified during construction. The inter -departmental coordination with Public Works <br />Facilities Division, Police and IT added time to the project. <br />c. Transformer relocation and electrical rerouting at restroom building. <br />The utility chase in the new restroom building houses many systems including a large portion of the <br />plumbing for the restroom and drinking fountains. It is the mechanical room for the water feature; it <br />includes a large sand filter and a UV filter, the backwash system for the water feature, the pipes and pump <br />for the treated grey water, the conduits for its electrical system and control panels. It also holds the <br />irrigation controller, the time -clocks for lighting and doors, and several electrical panels. The original <br />electrical plan showed the transformer inside the utility chase. Due to space restriction in the utility chase, <br />the transformer had to be relocated outside of the restroom building. The electrical plan revisions and <br />relocation work added time to the project. <br />2. Stainless Steel Slides <br />a. Material procurement delay due to City directed manufacturer change. <br />During construction, Magical Bridge Foundation (MBF) requested the City to change the slide <br />manufacturer from Goric to PlayWorld. At the time of the request, MBF was creating a line of play <br />equipment with PlayWorld, and due to their partnership, PlayWorld was able manufacture similar <br />products (seamless metal slides with smooth sides) at a reduced cost. However, the change of <br />manufacturer added additional time for design, production, delivery and installation. <br />Page 3 of 8 <br />City of Redwood City 1017 Middlefield Road, Redwood City, CA. 94063 Tel: 650-780-7000 www.redwoodcitV.org <br />223 <br />