REV: 10-25-2022 RLII. SCHEDULEConsultant shall follow the below project schedule, which may be amended with approval from the Public Works Director or their designee.Estimated dates for project deliverables include the following:• Completion of Tasks 2.1-2.2 (existing conditions, survey data): December 9th, 2022• Completion of Task 2.3 (vulnerability assessment): January 16th & February 6th, 2023• Completion of Task 3 (draft and final adaptation measures): March 20th & April 28th, 2023• Completion of Task 4 (draft and final sea-level rise adaptation report): May 22nd & June 30th, 2023ATTY/AGR.2022.381/Environmental Science Associates (Page 15 of 17)