Standard OSI Rev 12/2013 <br /> <br /> <br />F. The WP must include Contingency Plans for putting the Operating System back in <br />operation in case of an emergency or in case the Contractor fails to complete the work <br />within the Work Window. The Contingency Plans shall address the various stages of <br />activities to restore the System. <br /> <br />G. The WP’s must be of sufficient detail, clarity and organization to permit efficient review <br />by the Engineer and approval at least 10 calendar days before the proposed work is <br />performed. The WP shall be submitted to the Engineer as follows. <br /> <br />a) At least 21 calendar days prior to start of the subject work within the PCJPB Right of <br />Way for work other than signal and overhead wire installation. <br /> <br />b) At least 30 calendar days prior of the start of the work for work involving signal and <br />overhead wire installation, such as signal system cutover, overhead wire involving <br />third parties, etc. <br /> <br />H. The Engineer may request explanations and changes to the WP to ensure that it conforms <br />to the requirements of the Contract Documents. If the WP is not acceptable, Contractor <br />shall revise the WP to make it acceptable. The Contractor is responsible for submitting a <br />revised WP that can be reviewed and approved by the Engineer at least seven (7) days in <br />advance of any work within PCJPB Right of Way. <br /> <br />I. The Contractor will be informed if the WP is acceptable not less than seven (7) calendar <br />days prior to the scheduled start of work within the PCJPB Right of Way. Once the plan is <br />accepted, Contractor shall muster the resources necessary to perform the work <br />represented by the SSWP, so that necessary resources are available and ready for use, in <br />general on the day which begins the week in which the work is to be accomplished. At <br />this time, the Engineer will make a final decision as to whether or not the work is to <br />proceed as planned or will be canceled. The prime consideration will be the stage of <br />readiness of the Contractor, which the Contractor shall demonstrate to the Engineer. <br /> <br />1.04 WEEKLY SITE-SPECIFIC WORK PLAN (SSWP) <br /> <br />A. In addition to Work Plans, the Contractor shall submit a Site-Specific Work Plan (SSWP) on <br />a weekly basis three weeks in advance of the proposed work. All SSWPs shall detail the <br />proposed weekly events and activities, and include the Contractor’s request for Work <br />Windows. Approval of a WP or SSWP by the Engineer may require the placement of an <br />appropriate protective divider (k-rail, snow fence, etc.) between construction operations <br />and the operating system. Contractor shall furnish and install protective dividers as <br />specified by the Engineer. The Caltrain Project Manager will provide directions and <br />assistance to the Contractor in the preparation and submittal of the Site-Specific Work <br />Plan. <br />ATTY/AGR.2026.195/JPB License - Recycled Water at Beech (REV: 07-09-26 VR) (Page 24 of 29) <br />7.G. - Page 40 of 104 <br />138