I <br /> H. The Engineer may request explanations and changes to the WP to ensure that it conforms <br /> to the requirements of the Contract Documents. If the WP is not acceptable, Contractor <br /> shall revise the WP to make it acceptable. The Contractor is responsible for submitting a <br /> revised WP that can be reviewed and approved by the Engineer at least seven(7) days in <br /> advance of any work within PCJPB Right of Way. <br /> I. The Contractor will be informed if the WP is acceptable not less than seven(7) calendar <br /> days prior to the scheduled start of work within the PCJPB Right of Way. Once the plan is <br /> accepted, Contractor shall muster the resources necessary to perform the work represented <br /> by the SSWP, so that necessary resources are available and ready for use, in general on the <br /> day which begins the week in which the work is to be accomplished. At this time,the <br /> Engineer will make a final decision as to whether or not the work is to proceed as planned <br /> or will be canceled. The prime consideration will be the stage of readiness of the <br /> Contractor,which the Contractor shall demonstrate to the Engineer. <br /> 1.04 WEEKLY SITE SPECIFIC WORK PLAN (SSWP) Copy Included <br /> A. In addition to Work Plans, the Contractor shall submit a Site Specific Work P�an (SSWP) <br /> on a weekly basis three weeks in advance of the proposed work. All SSWP's shall detail <br /> the proposed weekly events and activities, and include the Contractor's request for Work <br /> Windows. Approval of a WP or SSWP by the Engineer may require the placement of an <br /> appropriate protective divider(k-rail, snow fence, etc.)between construction operations <br /> and the operating system. Contractor shall furnish and install protective dividers as <br /> specified by the Engineer. <br /> B. The Contractor shall furnish all labor,materials, and equipment as required to perform and <br /> complete the work within the approved work window. The Contractor shall maintain the <br /> approved schedule in the SSWP. <br /> C. All work outlined in the SSWP with a potential to impact normal functioning of any part <br /> of the operating system shall include a detailed schedule of events indicating the expected <br /> hourly progress of each activity that has a duration of one hour or longer. The schedule <br /> shall include a time at which all activities planned under the SSWP will be completed. The <br /> SSWP shall also include the mobile phone numbers of individuals responsible for <br /> compliance with the approved SSWP. Failure of the Contractor to complete the scheduled <br /> activities by the planned time or to put in place an approved contingency plan may <br /> adversely impact the operations of Caltrain. In the event that Caltrain service is delayed by <br /> Contractor's actions, damage will be incurred. Liquidated damages will be assessed as <br /> described in Exhibit C-1 Working Procedures. <br /> D. The SSWP shall be a plan that describes the activities necessary to perform the work <br /> within the Operating Envelope and indicates which Work Plans will be utilized. The plan <br /> shall explain each activity along with the proposed schedule to complete each item. Each <br /> activity in the plan shall include all material and equipment required to complete the <br /> activity within the scheduled time period. <br /> E. The SSWP shall also include contingency plans for putting the system back in operation <br /> in case of an emergency or in case the Contractor fails to perform and complete the work <br /> on time. Contingency plans shall address the various stages of construction. <br /> F. The contractor shall have a copy of the current Caltrain schedule. Schedules are available <br /> at Caltrain Stations or on the Internet at www.caltrain.com. <br />